Data record tests.energization-checks.ieee1547.enter-service

Verified 2026-10-24 Confidence: Medium

Clause 4.10 of IEEE 1547-2018 permits a DER to begin service only if permit service is enabled and the applicable voltage and frequency fall within the windows of Table 4, and then only after an intentional minimum delay, with active power rising linearly or in steps at a rate the clause bounds; clause 6.6 applies the same criteria to return to service after a trip.

ProvenanceIEEE 1547-2018 supports data record tests.energization-checks.ieee1547.enter-service, which is cited on the entry Energization Checks.SOURCEIEEE 1547-2018IEEE 1547-2018Licensed standard, clause 4.10.2, 4.10.3, Table 4, 6.6DATA RECORDtests.energization-checks.ieee1547.enter-servicetests.energization-check..Verified 2026-10-24ENTRYEnergization ChecksEnergization ChecksNo revisions
Provenance. Where this record comes from and where it is used: the cited source, the record itself and the entry that cites it.
Provenance: the chain from source to entry.
StepItemDetail
SourceIEEE 1547-2018Licensed standard, clause 4.10.2, 4.10.3, Table 4, 6.6
Data recordtests.energization-checks.ieee1547.enter-serviceVerified 2026-10-24
EntryEnergization ChecksNo revisions
Subject
Energization Checks (Test methods)
Kind
Method fact
Source
IEEE 1547-2018, clause 4.10.2, 4.10.3, Table 4, 6.6, Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces, IEEE.

History

Every recorded change to this data record, oldest first.
DateChange
2026-10-24created
2026-10-24revised
2026-10-24revised
2026-10-24review_status unreviewed -> software_reviewed

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"Data record tests.energization-checks.ieee1547.enter-service." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/data/tests.energization-checks.ieee1547.enter-service/.