Data record tests.insulation-resistance.osha-deenergize
Verified 2026-10-13 Confidence: High
Under 29 CFR 1910.333(a)(1), live parts to which an employee may be exposed are to be deenergized before the employee works on or near them, unless the employer shows that deenergizing creates added hazards or is infeasible.
| Step | Item | Detail |
|---|---|---|
| Source | 29 CFR 1910.333 | Regulation, clause 1910.333(a)(1) |
| Data record | tests.insulation-resistance.osha-deenergize | Verified 2026-10-13 |
| Entry | Insulation Resistance | 1 revision |
- Subject
- Insulation Resistance (Test methods)
- Kind
- Method fact
- Source
- 29 CFR 1910.333, current edition, clause 1910.333(a)(1), 1910.333 - Selection and use of work practices, OSHA. Regulation text. Agency copy of 29 CFR 1910.333
- Also stated in
- EM 385-1-1, section 11-4.c(4), page 212, the trailing cross-reference to 11-8.e(4) left off (15 March 2024).
Read the reference passage
11-4. Roles and Responsibilities. c. Host Employer
"If work must be performed on an energized system, then the host employer or system owner must first demonstrate that de-energizing introduces additional or increased hazards (for example, interruption of life support equipment, removal of light for an area) or is infeasible due to equipment design or operational limitations (for example, testing, troubleshooting)."
EM 385-1-1, section 11-4.c(4), page 212, the trailing cross-reference to 11-8.e(4) left off, 15 March 2024. Agency copy of EM 385-1-1
The current standard governs; this passage is a public-domain description of the practice dated 15 March 2024.
- EM 385-1-1, section 11-8.d, page 223, the paragraph's citation anchor kept inside the run; the ellipsis drops step (5), the test of each phase conductor with an adequately rated instrument, which names a standard (15 March 2024).
Read the reference passage
11-8. General Requirements. d. Establishing an Electrically Safe Work Condition (ESWC)
"All equipment and circuits must be de-energized before work is started unless energized work can be justified. A QP must complete and verify the following to establish electrically safe working conditions: (11-8.d) [...] (2) Control all sources of electrical energy to minimize employee exposure to electrical hazards. (3) Visually verify the disconnecting device is open or circuit breaker is withdrawn whenever possible. (4) Apply HEC devices (see chapter 12). [...] (6) Where induced voltages are possible, stored electrical energy exists, or if required within this chapter, ground the conductors or circuit parts before touching them."
EM 385-1-1, section 11-8.d, page 223, the paragraph's citation anchor kept inside the run; the ellipsis drops step (5), the test of each phase conductor with an adequately rated instrument, which names a standard, 15 March 2024. Agency copy of EM 385-1-1
The current standard governs; this passage is a public-domain description of the practice dated 15 March 2024.
- EM 385-1-1, section 11-4.c(4), page 212, the trailing cross-reference to 11-8.e(4) left off (15 March 2024).
History
| Date | Change |
|---|---|
| 2026-10-13 | created |
| 2026-10-13 | reviewed |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Data record tests.insulation-resistance.osha-deenergize." Electrical Testing Reference. 2026-10-13. https://www.electricaltestingreference.com/data/tests.insulation-resistance.osha-deenergize/.
Electrical Testing Reference, Data record tests.insulation-resistance.osha-deenergize (Oct. 13, 2026), https://www.electricaltestingreference.com/data/tests.insulation-resistance.osha-deenergize/.
@misc{etr-data-tests-insulation-resistance-osha-deenergize,
title = {Data record tests.insulation-resistance.osha-deenergize},
howpublished = {\url{https://www.electricaltestingreference.com/data/tests.insulation-resistance.osha-deenergize/}},
organization = {Electrical Testing Reference},
publisher = {Electrical Testing Reference},
year = {2026},
note = {last substantive change 2026-10-13}
}{{cite web |title=Data record tests.insulation-resistance.osha-deenergize |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/data/tests.insulation-resistance.osha-deenergize/ |date=2026-10-13 |access-date=}}