Data record tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats
Verified 2026-10-13 Confidence: Medium
Provenance pending: the source of this record has not yet been confirmed as official.
Phase Rotation and Phasing is addressed in ANSI/NETA ATS-2025.
| Step | Item | Detail |
|---|---|---|
| Source | ANSI/NETA ATS-2025 | Licensed standard, clause 7.22.3.B.7 |
| Data record | tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats | Verified 2026-10-13 |
| Entry | Phase Rotation and Phasing | No revisions |
- Subject
- Phase Rotation and Phasing (Test methods)
- Kind
- Method fact
- Source
- ANSI/NETA ATS-2025, clause 7.22.3.B.7, Acceptance Testing Specifications for Electrical Power Equipment and Systems, NETA. Publisher page for ANSI/NETA ATS-2025Publisher information page
- Also stated in
- FIST 4-7, section 6.1.55.1, page 147 (August 2023).
Read the reference passage
6.1.55.1 Phase Relation Test
"The phase relationship should be verified prior to energizing any equipment at system voltage. Phase Relation Tests are essential for PT circuits used for generator protection and synchronization. Automatic Synchronizers and Sync-check protective relays cannot detect a mis-aligned phase relationship and closing a generator out of phase could occur which may result in significant damage to equipment."
FIST 4-7, section 6.1.55.1, page 147, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 4-7, section 8.4.2, page 198 (August 2023).
Read the reference passage
8.4.2 Synchronization Test
"The swapping of leads of larger generators might have to be done on the high voltage side of the step-up transformer or at the generator terminals. It is good practice early on in the project, to confirm the phase rotation of the incoming transmission line to make sure it matches the correct phase rotation of the generator. It is easier to rotate the high voltage lines in the construction stage than during commissioning."
FIST 4-7, section 8.4.2, page 198, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 4-7, section 6.1.55.1, page 147 (August 2023).
History
| Date | Change |
|---|---|
| 2026-10-13 | created |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Data record tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats." Electrical Testing Reference. 2026-10-13. https://www.electricaltestingreference.com/data/tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats/.
Electrical Testing Reference, Data record tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats (Oct. 13, 2026), https://www.electricaltestingreference.com/data/tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats/.
@misc{etr-data-tests-phase-rotation-and-phasing-governed-by-ansi-neta-ats,
title = {Data record tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats},
howpublished = {\url{https://www.electricaltestingreference.com/data/tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats/}},
organization = {Electrical Testing Reference},
publisher = {Electrical Testing Reference},
year = {2026},
note = {last substantive change 2026-10-13}
}{{cite web |title=Data record tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/data/tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats/ |date=2026-10-13 |access-date=}}