Insulation Power Factor Dissipation Factor
Updated 2026-10-24
| Relationship | Entry |
|---|---|
| Governing standard | ANSI/NETA ATS-2025 (ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications) |
| Governing standard | ANSI/NETA MTS-2023 (ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications) |
Data records
- Insulation Power Factor Dissipation Factor is specified for outdoor bus structures in acceptance testing at clause 7.21.B.4 of ANSI/NETA ATS-2025. Value: outdoor bus structures.
- Insulation Power Factor Dissipation Factor is specified for outdoor bus structures in maintenance testing at clause 7.21.B.4 of ANSI/NETA MTS-2023. Value: outdoor bus structures.
- Insulation Power Factor Dissipation Factor is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.5 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors.
- Insulation Power Factor Dissipation Factor is specified for liquid-filled shunt and current-limiting reactors in maintenance testing at clause 7.20.3.2.B of ANSI/NETA MTS-2023. Value: liquid-filled shunt and current-limiting reactors.
- Insulation Power Factor Dissipation Factor is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.9 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers.
- Insulation Power Factor Dissipation Factor is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.9 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers.
- Insulation Power Factor Dissipation Factor is addressed in ANSI/NETA ATS-2025.
- Insulation Power Factor Dissipation Factor is addressed in ANSI/NETA MTS-2023.
- Clause 10.10 of IEEE C57.12.90-2021 runs the insulation power-factor test with all windings immersed and short-circuited and all bushings in place, inside a stated temperature band near room temperature with the top liquid temperature recorded, using a bridge or the volt-ampere-watt method at or near power frequency, at a test voltage capped at a fraction of the low-frequency test level or a fixed ceiling, whichever is lower.
- Table 4 of IEEE C57.12.90-2021 lists the insulation power-factor test connections for two-winding and three-winding transformers, with and without a guard circuit, and its footnote treats permanently connected windings such as those of autotransformers and regulators as a single winding.
- IEEE C57.12.90-2021 defines insulation power factor as the watts that the insulation dissipates divided by the volt-amperes applied to it, measured with a sinusoidal voltage under prescribed conditions, and states that the test applies to liquid-immersed distribution and power transformers of present-day design.
- Notes to Table 4 of IEEE C57.12.90-2021 explain why the code sets no standard insulation power-factor value for a liquid-immersed transformer: the quantity does not track dielectric withstand, its change with temperature is large and erratic, and it depends on the liquid and the materials used; the as-measured value is therefore reported together with the liquid temperature, the code advises against applying a temperature correction, and the factory reading becomes the baseline for later periodic comparisons.
- The test method is named Insulation Power Factor Dissipation Factor. Value: Insulation Power Factor Dissipation Factor.
Elsewhere in the family
- Insulation Power Factor Dissipation Factor more on this entry on Circuit Breaker Reference
- Insulation Power Factor Dissipation Factor more on this entry on Motor Testing Reference
- Insulation Power Factor Dissipation Factor more on this entry on Revenue Metering Reference
- Insulation Power Factor Dissipation Factor more on this entry on Switchgear Testing Reference
- Insulation Power Factor Dissipation Factor more on this entry on Transformer Testing Reference
- Dielectric loss related entry on Test Instrument Reference
- Tan delta related entry on Test Instrument Reference
- Power factor test set related entry on Test Instrument Reference
- IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers related entry on Transformer Testing Reference
Sources
- ANSI/NETA ATS-2025, Acceptance Testing Specifications for Electrical Power Equipment and Systems, 2025 edition, NETA. Cited: clause 7.21.B.4; clause 7.20.3.1.B.5; clause 7.24.2.B.9; clause 7.24.1.B.7. Held as: Purchased single-user copy. Publisher page for ANSI/NETA ATS-2025Publisher information page
- ANSI/NETA MTS-2023, Maintenance Testing Specifications for Electrical Power Equipment and Systems, 2023 edition, NETA. Cited: clause 7.21.B.4; clause 7.20.3.2.B; clause 7.24.2.B.9; clause 7.24.1.B.7. Held as: Purchased single-user copy. Publisher page for ANSI/NETA MTS-2023Publisher information page
- Electrical Testing Reference editorial taxonomy, Electrical Testing Reference editorial taxonomy of test methods, 2026-10 edition, Electrical Testing Reference. Held as: Own observation.
- IEEE C57.12.90-2021, Test Code for Liquid-Immersed Distribution, Power and Regulating Transformers, 2021 edition, IEEE. Cited: clause 10.10.1, 10.10.2, 10.10.3; clause 10.10.4, Table 4; clause 10.10; clause Table 4, Notes 2 and 3. Held as: Purchased single-user copy. Publisher page for IEEE C57.12.90-2021Publisher information page
Also stated in
- FIST 4-7, section 6.1.10.2, page 47 (August 2023).
Read the reference passage
6.1.10.2 Insulation Test
"Insulation power factor tests should be the final test prior to energization after all other tests are completed and the switchgear has been thoroughly cleaned to remove all construction dust and debris. Use only fluids or solvents specifically approved by the manufacturer."
FIST 4-7, section 6.1.10.2, page 47, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
Obtaining the documents
- ANSI/NETA ATS-2025: available from the publisher
- ANSI/NETA MTS-2023: available from the publisher
- IEEE C57.12.90-2021: available from the publisher
Changelog (19 entries)
| Date | Revision | Change |
|---|---|---|
| 2026-10-24 | created (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.conditions) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.conditions) | |
| 2026-10-24 | created (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.connections) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.connections) | |
| 2026-10-24 | created (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.definition) | |
| 2026-10-24 | revised (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.definition) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.definition) | |
| 2026-10-24 | created (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.no-standard-values) | |
| 2026-10-24 | revised (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.no-standard-values) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.no-standard-values) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.busway.acceptance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.busway.maintenance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.reactor.acceptance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.reactor.maintenance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.sectionalizer.acceptance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.equipment.sectionalizer.maintenance) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.governed-by.ansi-neta-ats) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.governed-by.ansi-neta-mts) | |
| 2026-10-13 | created (tests.insulation-power-factor-dissipation-factor.title) |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Insulation Power Factor Dissipation Factor." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/tests/insulation-power-factor-dissipation-factor/.
Electrical Testing Reference, Insulation Power Factor Dissipation Factor (Oct. 24, 2026), https://www.electricaltestingreference.com/tests/insulation-power-factor-dissipation-factor/.
@misc{etr-tests-insulation-power-factor-dissipation-factor,
title = {Insulation Power Factor Dissipation Factor},
howpublished = {\url{https://www.electricaltestingreference.com/tests/insulation-power-factor-dissipation-factor/}},
organization = {Electrical Testing Reference},
publisher = {Electrical Testing Reference},
year = {2026},
note = {last substantive change 2026-10-24}
}{{cite web |title=Insulation Power Factor Dissipation Factor |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/tests/insulation-power-factor-dissipation-factor/ |date=2026-10-24 |access-date=}}