SCADA and Communication Verification
Updated 2026-10-24
| Relationship | Entry |
|---|---|
| Governing standard | ANSI/NETA ATS-2025 (ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications) |
| Governing standard | ANSI/NETA MTS-2023 (ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications) |
Data records
- SCADA and Communication Verification is specified for complete electrical systems in maintenance testing at clause 8 of ANSI/NETA MTS-2023. Value: complete electrical systems.
- SCADA and Communication Verification is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.10 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems.
- SCADA and Communication Verification is addressed in ANSI/NETA ATS-2025.
- SCADA and Communication Verification is addressed in ANSI/NETA MTS-2023.
- Clause 4.5 of IEEE 2800-2022 requires a secure bidirectional local communication interface at the plant, with protocols and data items set by the interconnection agreement and cyber security measures; Table 20 lists this capability among those verified by commissioning tests, and the method of verification is by mutual agreement.
- The test method is named SCADA and Communication Verification. Value: SCADA and Communication Verification.
Elsewhere in the family
- SCADA and Communication Verification more on this entry on Protective Relay Reference
- Meter Accuracy Verification related entry on Revenue Metering Reference
- Arc Energy Reduction Performance related entry on Arc Flash Reference
- Protective relay test set related entry on Test Instrument Reference
- IEEE Standard for Interconnection and Interoperability of Inverter-Based Resources (IBRs) Interconnecting with Associated Transmission Electric Power Systems related entry on Interconnection Reference
Sources
- ANSI/NETA ATS-2025, Acceptance Testing Specifications for Electrical Power Equipment and Systems, 2025 edition, NETA. Cited: clause 7.29.B.10; clause 7.9.2.B.10. Held as: Purchased single-user copy. Publisher page for ANSI/NETA ATS-2025Publisher information page
- ANSI/NETA MTS-2023, Maintenance Testing Specifications for Electrical Power Equipment and Systems, 2023 edition, NETA. Cited: clause 8. Held as: Purchased single-user copy. Publisher page for ANSI/NETA MTS-2023Publisher information page
- Electrical Testing Reference editorial taxonomy, Electrical Testing Reference editorial taxonomy of test methods, 2026-10 edition, Electrical Testing Reference. Held as: Own observation.
- IEEE 2800-2022, Interconnection and Interoperability of Inverter-Based Resources with Transmission Systems, 2022 edition, IEEE. Cited: clause 4.5, 12.3.2. Held as: Purchased single-user copy. Publisher page for IEEE 2800-2022Publisher information page
Also stated in
- FIST 4-7, section 6.1.12, page 53 (August 2023).
Read the reference passage
6.1.12 Control and SCADA Systems
"A thorough pre-commissioning test plan should be created in advance of any testing. No actual plant operations will be performed as part of this test plan. Operations should be simulated. Portions of this test plan can be performed as part of the Factory Acceptance Test (FAT) prior to pre-commissioning if needed, provided that the FAT test results are documented."
FIST 4-7, section 6.1.12, page 53, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 4-7, section 7.5.4, page 160 (August 2023).
Read the reference passage
7.5.4 Verify Unit Control by HMI/SCADA System (Local and Remote)
"The most important test would be to confirm bumpless transfer when switching between local and remote (with the unit in simulated power production)."
FIST 4-7, section 7.5.4, page 160, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 4-7, section 6.1.18.1, page 62 (August 2023).
Read the reference passage
6.1.18.1 Control System Tests
"System checkout also includes functional verification of inter-device communication and time synchronization. Firmware should be verified to be the correct version and any cyber security systems to be functional."
FIST 4-7, section 6.1.18.1, page 62, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
Obtaining the documents
- ANSI/NETA ATS-2025: available from the publisher
- ANSI/NETA MTS-2023: available from the publisher
- IEEE 2800-2022: available from the publisher
Changelog (8 entries)
| Date | Revision | Change |
|---|---|---|
| 2026-10-24 | created (tests.scada-and-communication-verification.ieee2800.communication-interface) | |
| 2026-10-24 | revised (tests.scada-and-communication-verification.ieee2800.communication-interface) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.scada-and-communication-verification.ieee2800.communication-interface) | |
| 2026-10-13 | created (tests.scada-and-communication-verification.equipment.commissioning-system.maintenance) | |
| 2026-10-13 | created (tests.scada-and-communication-verification.equipment.solar.acceptance) | |
| 2026-10-13 | created (tests.scada-and-communication-verification.governed-by.ansi-neta-ats) | |
| 2026-10-13 | created (tests.scada-and-communication-verification.governed-by.ansi-neta-mts) | |
| 2026-10-13 | created (tests.scada-and-communication-verification.title) |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"SCADA and Communication Verification." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/tests/scada-and-communication-verification/.
Electrical Testing Reference, SCADA and Communication Verification (Oct. 24, 2026), https://www.electricaltestingreference.com/tests/scada-and-communication-verification/.
@misc{etr-tests-scada-and-communication-verification,
title = {SCADA and Communication Verification},
howpublished = {\url{https://www.electricaltestingreference.com/tests/scada-and-communication-verification/}},
organization = {Electrical Testing Reference},
publisher = {Electrical Testing Reference},
year = {2026},
note = {last substantive change 2026-10-24}
}{{cite web |title=SCADA and Communication Verification |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/tests/scada-and-communication-verification/ |date=2026-10-24 |access-date=}}