SCADA and Communication Verification

Updated 2026-10-24

RelationshipsSCADA and Communication Verification is governed by ANSI/NETA ATS-2025, ANSI/NETA MTS-2023 and applies to no listed equipment.ANSI/NETA ATS-2025 Standard for Acceptance Testing SpecificationsANSI/NETA ATS-2025ANSI/NETA MTS-2023 Standard for Maintenance Testing SpecificationsANSI/NETA MTS-2023SCADA and Communication VerificationSCADA and Communication Verification
Relationships. Governing standards on the left, equipment classes the test applies to on the right, as recorded for this entry.
Relationships: relationships recorded for this entry.
RelationshipEntry
Governing standardANSI/NETA ATS-2025 (ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications)
Governing standardANSI/NETA MTS-2023 (ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications)

Data records

Sources

  • ANSI/NETA ATS-2025, Acceptance Testing Specifications for Electrical Power Equipment and Systems, 2025 edition, NETA. Cited: clause 7.29.B.10; clause 7.9.2.B.10. Held as: Purchased single-user copy. Publisher page for ANSI/NETA ATS-2025Publisher information page
  • ANSI/NETA MTS-2023, Maintenance Testing Specifications for Electrical Power Equipment and Systems, 2023 edition, NETA. Cited: clause 8. Held as: Purchased single-user copy. Publisher page for ANSI/NETA MTS-2023Publisher information page
  • Electrical Testing Reference editorial taxonomy, Electrical Testing Reference editorial taxonomy of test methods, 2026-10 edition, Electrical Testing Reference. Held as: Own observation.
  • IEEE 2800-2022, Interconnection and Interoperability of Inverter-Based Resources with Transmission Systems, 2022 edition, IEEE. Cited: clause 4.5, 12.3.2. Held as: Purchased single-user copy. Publisher page for IEEE 2800-2022Publisher information page

Also stated in

  • FIST 4-7, section 6.1.12, page 53 (August 2023).
    Read the reference passage

    6.1.12 Control and SCADA Systems

    "A thorough pre-commissioning test plan should be created in advance of any testing. No actual plant operations will be performed as part of this test plan. Operations should be simulated. Portions of this test plan can be performed as part of the Factory Acceptance Test (FAT) prior to pre-commissioning if needed, provided that the FAT test results are documented."

    FIST 4-7, section 6.1.12, page 53, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

  • FIST 4-7, section 7.5.4, page 160 (August 2023).
    Read the reference passage

    7.5.4 Verify Unit Control by HMI/SCADA System (Local and Remote)

    "The most important test would be to confirm bumpless transfer when switching between local and remote (with the unit in simulated power production)."

    FIST 4-7, section 7.5.4, page 160, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

  • FIST 4-7, section 6.1.18.1, page 62 (August 2023).
    Read the reference passage

    6.1.18.1 Control System Tests

    "System checkout also includes functional verification of inter-device communication and time synchronization. Firmware should be verified to be the correct version and any cyber security systems to be functional."

    FIST 4-7, section 6.1.18.1, page 62, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

Obtaining the documents

Changelog (8 entries)
DateRevisionChange
2026-10-24created (tests.scada-and-communication-verification.ieee2800.communication-interface)
2026-10-24revised (tests.scada-and-communication-verification.ieee2800.communication-interface)
2026-10-24review_status unreviewed -> software_reviewed (tests.scada-and-communication-verification.ieee2800.communication-interface)
2026-10-13created (tests.scada-and-communication-verification.equipment.commissioning-system.maintenance)
2026-10-13created (tests.scada-and-communication-verification.equipment.solar.acceptance)
2026-10-13created (tests.scada-and-communication-verification.governed-by.ansi-neta-ats)
2026-10-13created (tests.scada-and-communication-verification.governed-by.ansi-neta-mts)
2026-10-13created (tests.scada-and-communication-verification.title)

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"SCADA and Communication Verification." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/tests/scada-and-communication-verification/.
Electrical Testing Reference, SCADA and Communication Verification (Oct. 24, 2026), https://www.electricaltestingreference.com/tests/scada-and-communication-verification/.
@misc{etr-tests-scada-and-communication-verification,
  title = {SCADA and Communication Verification},
  howpublished = {\url{https://www.electricaltestingreference.com/tests/scada-and-communication-verification/}},
  organization = {Electrical Testing Reference},
  publisher = {Electrical Testing Reference},
  year = {2026},
  note = {last substantive change 2026-10-24}
}
{{cite web |title=SCADA and Communication Verification |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/tests/scada-and-communication-verification/ |date=2026-10-24 |access-date=}}