System Function Testing

Updated 2026-10-24

RelationshipsSystem Function Testing is governed by ANSI/NETA ATS-2025, ANSI/NETA MTS-2023 and applies to no listed equipment.ANSI/NETA ATS-2025 Standard for Acceptance Testing SpecificationsANSI/NETA ATS-2025ANSI/NETA MTS-2023 Standard for Maintenance Testing SpecificationsANSI/NETA MTS-2023System Function TestingSystem Function Testing
Relationships. Governing standards on the left, equipment classes the test applies to on the right, as recorded for this entry.
Relationships: relationships recorded for this entry.
RelationshipEntry
Governing standardANSI/NETA ATS-2025 (ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications)
Governing standardANSI/NETA MTS-2023 (ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications)

Data records

  • System Function Testing is specified for complete electrical systems in acceptance testing at clause 8 of ANSI/NETA ATS-2025. Value: complete electrical systems. Source: ANSI/NETA ATS-2025, clause 8. Verified 2026-10-13. Record tests.system-function-testing.equipment.commissioning-system.acceptance
  • System Function Testing is specified for complete electrical systems in maintenance testing at clause 8 of ANSI/NETA MTS-2023. Value: complete electrical systems. Source: ANSI/NETA MTS-2023, clause 8. Verified 2026-10-13. Record tests.system-function-testing.equipment.commissioning-system.maintenance
  • System Function Testing is specified for electric vehicle charging systems in acceptance testing at clause 7.26.B.1 of ANSI/NETA ATS-2025. Value: electric vehicle charging systems. Source: ANSI/NETA ATS-2025, clause 7.26.B.1. Verified 2026-10-13. Record tests.system-function-testing.equipment.evcharging.acceptance
  • System Function Testing is specified for electric vehicle charging systems in maintenance testing at clause 7.26.B.2 of ANSI/NETA MTS-2023. Value: electric vehicle charging systems. Source: ANSI/NETA MTS-2023, clause 7.26.B.2. Verified 2026-10-13. Record tests.system-function-testing.equipment.evcharging.maintenance
  • System Function Testing is addressed in ANSI/NETA ATS-2025. Source: ANSI/NETA ATS-2025, clause 8. Verified 2026-10-13. Record tests.system-function-testing.governed-by.ansi-neta-ats
  • System Function Testing is addressed in ANSI/NETA MTS-2023. Source: ANSI/NETA MTS-2023, clause 8. Verified 2026-10-13. Record tests.system-function-testing.governed-by.ansi-neta-mts
  • Table 71 in clause 8.1.3.4.1 of IEEE 1547.1-2020 distinguishes a basic commissioning test, which may consist of a visual inspection together with an operability check of the isolation device and whose scope the design evaluation sets, from a detailed commissioning test, which adds functional tests of the combined devices. Source: IEEE 1547.1-2020, clause 8.1.3.4.1. Verified 2026-10-24. Record tests.system-function-testing.ieee1547-1.commissioning-scope
  • Commissioning test CT1 in clause 8.2.3.1 of IEEE 1547.1-2020 is an on-off test: the DER is brought online from off in the specified mode while the voltage response of the Area EPS, the intentional delay and the ramp to steady state are observed, a disconnect and reconnect are simulated, and cease to energize is verified when all ungrounded phases are opened by some device other than the interconnection device and, for multiphase DER, when one phase is opened at the PoC. Observations are reviewed with the Area EPS operator, results are documented with the agreement of both operators, and any failure carries agreed corrective action and a repeat of the test. Source: IEEE 1547.1-2020, clause 8.2.3.1. Verified 2026-10-24. Record tests.system-function-testing.ieee1547-1.on-off-test
  • Under clause 9 of IEEE 1547.1-2020, periodic re-verification of a DER uses the clause 8 field methods as agreed between the operators, and the Area EPS operator receives documentation of the updated configuration together with the re-verification results. Source: IEEE 1547.1-2020, clause 9. Verified 2026-10-24. Record tests.system-function-testing.ieee1547-1.periodic-reverification
  • Clause 11.2.5 of IEEE 1547-2018 requires DER commissioning tests to follow written procedures from the manufacturer or system designer that the owner and the area electric power system operator have approved, always to include a visual inspection, and distinguishes a basic commissioning test (visual inspection plus operability of the isolation device) from a detailed one that adds functional tests of the interconnection devices as a system. Source: IEEE 1547-2018, clause 11.2.5. Verified 2026-10-24. Record tests.system-function-testing.ieee1547.commissioning-tests
  • Clause 12.2.5 of IEEE 2800-2022 defines a commissioning test as a field verification of a unit, a supplemental device or the whole plant, run in every case to a written procedure that follows good engineering practice and that the transmission system operator has accepted as suited to the requirement; such tests may include operability and functional performance tests. Source: IEEE 2800-2022, clause 12.2.5. Verified 2026-10-24. Record tests.system-function-testing.ieee2800.commissioning-tests
  • The test method is named System Function Testing. Value: System Function Testing. Source: Electrical Testing Reference editorial taxonomy, 2026-10 edition. Verified 2026-10-13. Record tests.system-function-testing.title

Sources

Also stated in

  • FIST 4-7, section 7.2, page 157 (August 2023).
    Read the reference passage

    7.2 Functional Testing

    "The concept behind functional testing is to test the entire system as a whole. The purpose is to verify as much as possible by simulating real operation. This will identify, to the greatest extent possible, any problems and issues before electrical energy and rotation is applied to the unit."

    FIST 4-7, section 7.2, page 157, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

  • FIST 4-7, section 3.4, page 9 (August 2023).
    Read the reference passage

    3.4 Commissioning Plan

    "The purpose of the functional testing is to ensure each system and its components perform in accordance with design requirements and is complete and safe to energize or operate."

    FIST 4-7, section 3.4, page 9, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

  • FIST 4-7, section 7.2, page 157 (August 2023).
    Read the reference passage

    7.2 Functional Testing

    "Functional testing can be done in parts, but the goal is to eventually carry out a complete start to 100% load and back to stop simulation of the unit."

    FIST 4-7, section 7.2, page 157, August 2023. Agency copy of FIST 4-7

    The current standard governs; this passage is a public-domain description of the practice dated August 2023.

Obtaining the documents

Changelog (21 entries)
DateRevisionChange
2026-10-24created (tests.system-function-testing.ieee1547-1.commissioning-scope)
2026-10-24revised (tests.system-function-testing.ieee1547-1.commissioning-scope)
2026-10-24review_status unreviewed -> software_reviewed (tests.system-function-testing.ieee1547-1.commissioning-scope)
2026-10-24created (tests.system-function-testing.ieee1547-1.on-off-test)
2026-10-24revised (tests.system-function-testing.ieee1547-1.on-off-test)
2026-10-24review_status unreviewed -> software_reviewed (tests.system-function-testing.ieee1547-1.on-off-test)
2026-10-24created (tests.system-function-testing.ieee1547-1.periodic-reverification)
2026-10-24revised (tests.system-function-testing.ieee1547-1.periodic-reverification)
2026-10-24review_status unreviewed -> software_reviewed (tests.system-function-testing.ieee1547-1.periodic-reverification)
2026-10-24created (tests.system-function-testing.ieee1547.commissioning-tests)
2026-10-24review_status unreviewed -> software_reviewed (tests.system-function-testing.ieee1547.commissioning-tests)
2026-10-24created (tests.system-function-testing.ieee2800.commissioning-tests)
2026-10-24revised (tests.system-function-testing.ieee2800.commissioning-tests)
2026-10-24review_status unreviewed -> software_reviewed (tests.system-function-testing.ieee2800.commissioning-tests)
2026-10-13created (tests.system-function-testing.equipment.commissioning-system.acceptance)
2026-10-13created (tests.system-function-testing.equipment.commissioning-system.maintenance)
2026-10-13created (tests.system-function-testing.equipment.evcharging.acceptance)
2026-10-13created (tests.system-function-testing.equipment.evcharging.maintenance)
2026-10-13created (tests.system-function-testing.governed-by.ansi-neta-ats)
2026-10-13created (tests.system-function-testing.governed-by.ansi-neta-mts)
2026-10-13created (tests.system-function-testing.title)

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"System Function Testing." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/tests/system-function-testing/.
Electrical Testing Reference, System Function Testing (Oct. 24, 2026), https://www.electricaltestingreference.com/tests/system-function-testing/.
@misc{etr-tests-system-function-testing,
  title = {System Function Testing},
  howpublished = {\url{https://www.electricaltestingreference.com/tests/system-function-testing/}},
  organization = {Electrical Testing Reference},
  publisher = {Electrical Testing Reference},
  year = {2026},
  note = {last substantive change 2026-10-24}
}
{{cite web |title=System Function Testing |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/tests/system-function-testing/ |date=2026-10-24 |access-date=}}