| Relationship | Entry |
|---|---|
| Governing standard | ANSI/NETA ATS-2025 (ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications) |
| Governing standard | ANSI/NETA MTS-2023 (ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications) |
Data records
- Winding Resistance is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.3 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors.
- Winding Resistance is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.3 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors.
- Winding Resistance is addressed in ANSI/NETA ATS-2025.
- Winding Resistance is addressed in ANSI/NETA MTS-2023.
- Winding Resistance is addressed in IEEE C57.13-2016.
- Winding Resistance is addressed in IEEE C57.13.1-2017.
- Winding Resistance is addressed in IEEE/IEC C57.15-2017.
- Clause 5.1 of IEEE C57.12.90-2021 lets the winding temperature for a resistance measurement be taken as the average liquid temperature only after the transformer has stood without excitation or load current for a stated settling period and the top-to-bottom liquid temperature difference is inside a stated limit; windings out of liquid take the average of several thermometers or thermocouples set among the coils and touching the conductors.
- Clause 5.3.1 of IEEE C57.12.90-2021 measures winding resistance by the direct-current voltmeter-ammeter method with simultaneous voltage and current readings and with voltmeter leads separate from the current leads and connected at the winding terminals, while clause 5.3.2 allows bridge methods.
- Clause 5.3.1 of IEEE C57.12.90-2021 takes readings only after the current and voltage have settled, averages several readings, limits the test current to a stated fraction of the rated winding current so that heating does not change the resistance, and magnetizes the core to saturation with direct current first so that a cold measurement and a hot measurement start from the same residual flux.
- Clause 5.2 of IEEE C57.12.90-2021 converts a measured winding resistance to the reference temperature with a formula whose material constant differs between copper and aluminum conductors, so the conductor material is part of the record.
- The test method is named Winding Resistance. Value: Winding Resistance.
Elsewhere in the family
- Winding Resistance more on this entry on Motor Testing Reference
- Winding Resistance more on this entry on Transformer Testing Reference
- Dynamic Winding Resistance related entry on Transformer Testing Reference
- Field Pole Voltage Drop related entry on Motor Testing Reference
- Battery Intercell Connection Resistance related entry on Battery Testing Reference
- Winding resistance meter related entry on Test Instrument Reference
- IEEE Standard Requirements for Instrument Transformers related entry on Revenue Metering Reference
- IEEE Guide for Field Testing of Relaying Current Transformers related entry on Revenue Metering Reference
- IEEE/IEC International Standard: Power transformers, Part 21: Standard requirements, terminology, and test code for step-voltage regulators related entry on Transformer Testing Reference
- IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers related entry on Transformer Testing Reference
Sources
- ANSI/NETA ATS-2025, Acceptance Testing Specifications for Electrical Power Equipment and Systems, 2025 edition, NETA. Cited: clause 7.20.3.1.B.3; clause 7.15.1.B.4. Held as: Purchased single-user copy. Publisher page for ANSI/NETA ATS-2025Publisher information page
- ANSI/NETA MTS-2023, Maintenance Testing Specifications for Electrical Power Equipment and Systems, 2023 edition, NETA. Cited: clause 7.20.3.1.B.3; clause 7.15.2.B. Held as: Purchased single-user copy. Publisher page for ANSI/NETA MTS-2023Publisher information page
- Electrical Testing Reference editorial taxonomy, Electrical Testing Reference editorial taxonomy of test methods, 2026-10 edition, Electrical Testing Reference. Held as: Own observation.
- IEEE C57.12.90-2021, Test Code for Liquid-Immersed Distribution, Power and Regulating Transformers, 2021 edition, IEEE. Cited: clause 5.1; clause 5.3.1, 5.3.2; clause 5.3.1; clause 5.2. Held as: Purchased single-user copy. Publisher page for IEEE C57.12.90-2021Publisher information page
- IEEE C57.13-2016, Requirements for Instrument Transformers, 2016 edition, IEEE. Cited: clause 6.4.1.4. Held as: Purchased single-user copy. Publisher page for IEEE C57.13-2016Publisher information page
- IEEE C57.13.1-2017, Guide for Field Testing of Relaying Current Transformers, 2017 edition, IEEE. Cited: clause 11. Held as: Purchased single-user copy. Publisher page for IEEE C57.13.1-2017Publisher information page
- IEEE/IEC C57.15-2017, Requirements, Terminology and Test Code for Step-Voltage Regulators, 2017 edition, IEEE. Cited: clause 9.2. Held as: Purchased single-user copy. Publisher page for IEEE/IEC C57.15-2017Publisher information page
Also stated in
- FIST 4-7, section 6.1.28, page 83 (August 2023).
Read the reference passage
6.1.28 Generator and Large Motor Windings
"Winding (copper) temperature impacts the calculated resistance value, so it is important to record the RTD temperature of the stator windings and then normalize the results to a standard temperature. This allows for comparison to manufacturer's design values and for comparison to future maintenance testing. Issues detected with this test often are due to improperly brazed connections between stator coils or bars, or improperly made bolted electrical connections at the generator terminals."
FIST 4-7, section 6.1.28, page 83, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 4-7, section 6.1.28.5, page 90 (August 2023).
Read the reference passage
6.1.28.5 Conductor Resistance Testing
"Because the resistance of copper is affected by temperature, the data should be corrected to a constant temperature for trending and comparison purposes. Sufficient time should be allowed to permit the reading to stabilize before recording the data due to the inductive nature of most stator and rotor windings."
FIST 4-7, section 6.1.28.5, page 90, August 2023. Agency copy of FIST 4-7
The current standard governs; this passage is a public-domain description of the practice dated August 2023.
- FIST 3-8, appendix D, page 85 (May 2011 (minor revisions 09/27/2021)).
Read the reference passage
Appendix D - Instrument Transformer Burden Measurements for Current Transformers and Potential Transformers
"The internal CT burden is the resistance of the secondary winding. Measuring the internal resistance of the CT secondary winding can be accomplished with a digital ohmmeter."
FIST 3-8, appendix D, page 85, May 2011 (minor revisions 09/27/2021). Agency copy of FIST 3-8
The current standard governs; this passage is a public-domain description of the practice dated May 2011 (minor revisions 09/27/2021).
- FIST 3-30, section 4.7.1, page 76 (October 2000).
Read the reference passage
4.7.1 Winding Resistances
"You may have to convert resistance measurements to the reference temperature used at the factory (usually 75 °C) to compare your resistance measurements to the factory results."
FIST 3-30, section 4.7.1, page 76, October 2000. Agency copy of FIST 3-30
The current standard governs; this passage is a public-domain description of the practice dated October 2000.
Obtaining the documents
- ANSI/NETA ATS-2025: available from the publisher
- ANSI/NETA MTS-2023: available from the publisher
- IEEE C57.12.90-2021: available from the publisher
- IEEE C57.13-2016: available from the publisher
- IEEE C57.13.1-2017: available from the publisher
- IEEE/IEC C57.15-2017: available from the publisher
Changelog (18 entries)
| Date | Revision | Change |
|---|---|---|
| 2026-10-24 | created (tests.winding-resistance.ieeec57-12-90.cold-temperature) | |
| 2026-10-24 | revised (tests.winding-resistance.ieeec57-12-90.cold-temperature) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.winding-resistance.ieeec57-12-90.cold-temperature) | |
| 2026-10-24 | created (tests.winding-resistance.ieeec57-12-90.method) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.winding-resistance.ieeec57-12-90.method) | |
| 2026-10-24 | created (tests.winding-resistance.ieeec57-12-90.readings) | |
| 2026-10-24 | revised (tests.winding-resistance.ieeec57-12-90.readings) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.winding-resistance.ieeec57-12-90.readings) | |
| 2026-10-24 | created (tests.winding-resistance.ieeec57-12-90.reference-temperature) | |
| 2026-10-24 | review_status unreviewed -> software_reviewed (tests.winding-resistance.ieeec57-12-90.reference-temperature) | |
| 2026-10-13 | created (tests.winding-resistance.equipment.reactor.acceptance) | |
| 2026-10-13 | created (tests.winding-resistance.equipment.reactor.maintenance) | |
| 2026-10-13 | created (tests.winding-resistance.governed-by.ansi-neta-ats) | |
| 2026-10-13 | created (tests.winding-resistance.governed-by.ansi-neta-mts) | |
| 2026-10-13 | created (tests.winding-resistance.governed-by.ieee-c57-13) | |
| 2026-10-13 | created (tests.winding-resistance.governed-by.ieee-c57-13-1) | |
| 2026-10-13 | created (tests.winding-resistance.governed-by.ieee-c57-15) | |
| 2026-10-13 | created (tests.winding-resistance.title) |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Winding Resistance." Electrical Testing Reference. 2026-10-24. https://www.electricaltestingreference.com/tests/winding-resistance/.
Electrical Testing Reference, Winding Resistance (Oct. 24, 2026), https://www.electricaltestingreference.com/tests/winding-resistance/.
@misc{etr-tests-winding-resistance,
title = {Winding Resistance},
howpublished = {\url{https://www.electricaltestingreference.com/tests/winding-resistance/}},
organization = {Electrical Testing Reference},
publisher = {Electrical Testing Reference},
year = {2026},
note = {last substantive change 2026-10-24}
}{{cite web |title=Winding Resistance |website=Electrical Testing Reference |publisher=Electrical Testing Reference |url=https://www.electricaltestingreference.com/tests/winding-resistance/ |date=2026-10-24 |access-date=}}