Data records: Test methods
415 records across 48 subjects. Each subject's records follow, one table per subject. Last change 2026-11-02.
Bolted Connection Resistance
| Record | Statement |
|---|---|
| tests.bolted-connection-resistance.equipment.ats-transfer.acceptance | Bolted Connection Resistance is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.B.1 of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.bolted-connection-resistance.equipment.ats-transfer.maintenance | Bolted Connection Resistance is specified for automatic transfer switches in emergency systems in maintenance testing at clause 7.22.3.B.1 of ANSI/NETA MTS-2023. Value: automatic transfer switches in emergency systems. |
| tests.bolted-connection-resistance.equipment.busway-enclosed.acceptance | Bolted Connection Resistance is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.1 of ANSI/NETA ATS-2025. The clause calls for resistance measurements through the bolted connections and bus joints with a low-resistance ohmmeter. Value: metal-enclosed busways. |
| tests.bolted-connection-resistance.equipment.busway.acceptance | Bolted Connection Resistance is specified for outdoor bus structures in acceptance testing at clause 7.21.B.1 of ANSI/NETA ATS-2025. Value: outdoor bus structures. |
| tests.bolted-connection-resistance.equipment.busway.maintenance | Bolted Connection Resistance is specified for outdoor bus structures in maintenance testing at clause 7.21.B.1 of ANSI/NETA MTS-2023. Value: outdoor bus structures. |
| tests.bolted-connection-resistance.equipment.capacitor.acceptance | Bolted Connection Resistance is specified for capacitors in acceptance testing at clause 7.20.1.B.1 of ANSI/NETA ATS-2025. Value: capacitors. |
| tests.bolted-connection-resistance.equipment.capacitor.maintenance | Bolted Connection Resistance is specified for capacitors in maintenance testing at clause 7.20.1.B.1 of ANSI/NETA MTS-2023. Value: capacitors. |
| tests.bolted-connection-resistance.equipment.drive.acceptance | Bolted Connection Resistance is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.B.1 of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.bolted-connection-resistance.equipment.drive.maintenance | Bolted Connection Resistance is specified for adjustable-speed drive systems in maintenance testing at clause 7.17.B.1 of ANSI/NETA MTS-2023. Value: adjustable-speed drive systems. |
| tests.bolted-connection-resistance.equipment.evcharging.maintenance | Bolted Connection Resistance is specified for electric vehicle charging systems in maintenance testing at clause 7.26.B.1 of ANSI/NETA MTS-2023. Value: electric vehicle charging systems. |
| tests.bolted-connection-resistance.equipment.network-protector.acceptance | Bolted Connection Resistance is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.1 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.bolted-connection-resistance.equipment.network-protector.maintenance | Bolted Connection Resistance is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.1 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.bolted-connection-resistance.equipment.reactor.acceptance | Bolted Connection Resistance is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.1 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.bolted-connection-resistance.equipment.reactor.maintenance | Bolted Connection Resistance is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.1 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.bolted-connection-resistance.equipment.resistor.acceptance | Bolted Connection Resistance is specified for resistors in acceptance testing at clause 7.20.4.B.1 of ANSI/NETA ATS-2025. Value: resistors. |
| tests.bolted-connection-resistance.equipment.resistor.maintenance | Bolted Connection Resistance is specified for resistors in maintenance testing at clause 7.20.4.B.1 of ANSI/NETA MTS-2023. Value: resistors. |
| tests.bolted-connection-resistance.equipment.sectionalizer.acceptance | Bolted Connection Resistance is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.1 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.bolted-connection-resistance.equipment.sectionalizer.maintenance | Bolted Connection Resistance is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.1 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.bolted-connection-resistance.equipment.surge.acceptance | Bolted Connection Resistance is specified for medium-voltage and high-voltage surge arresters in acceptance testing at clause 7.19.2.B.1 of ANSI/NETA ATS-2025. Value: medium-voltage and high-voltage surge arresters. |
| tests.bolted-connection-resistance.equipment.surge.maintenance | Bolted Connection Resistance is specified for low-voltage surge protective devices in maintenance testing at clause 7.19.1.B.1 of ANSI/NETA MTS-2023. Value: low-voltage surge protective devices. |
| tests.bolted-connection-resistance.equipment.ups.acceptance | Bolted Connection Resistance is specified for uninterruptible power systems in acceptance testing at clause 7.22.2.B.1 of ANSI/NETA ATS-2025. Value: uninterruptible power systems. |
| tests.bolted-connection-resistance.equipment.ups.maintenance | Bolted Connection Resistance is specified for uninterruptible power systems in maintenance testing at clause 7.22.2.B.1 of ANSI/NETA MTS-2023. Value: uninterruptible power systems. |
| tests.bolted-connection-resistance.governed-by.ansi-neta-ats | Bolted Connection Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.bolted-connection-resistance.governed-by.ansi-neta-mts | Bolted Connection Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.bolted-connection-resistance.title | The test method is named Bolted Connection Resistance. Value: Bolted Connection Resistance. |
Bushing Power Factor and Capacitance
| Record | Statement |
|---|---|
| tests.bushing-power-factor-and-capacitance.equipment.reactor.acceptance | Bushing Power Factor and Capacitance is specified for liquid-filled shunt and current-limiting reactors in acceptance testing at clause 7.20.3.2.B.4 of ANSI/NETA ATS-2025. Value: liquid-filled shunt and current-limiting reactors. |
| tests.bushing-power-factor-and-capacitance.equipment.reactor.maintenance | Bushing Power Factor and Capacitance is specified for liquid-filled shunt and current-limiting reactors in maintenance testing at clause 7.20.3.2.B of ANSI/NETA MTS-2023. Value: liquid-filled shunt and current-limiting reactors. |
| tests.bushing-power-factor-and-capacitance.equipment.sectionalizer.acceptance | Bushing Power Factor and Capacitance is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.10 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.bushing-power-factor-and-capacitance.equipment.sectionalizer.maintenance | Bushing Power Factor and Capacitance is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.10 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.bushing-power-factor-and-capacitance.governed-by.ansi-neta-ats | Bushing Power Factor and Capacitance is addressed in ANSI/NETA ATS-2025. |
| tests.bushing-power-factor-and-capacitance.governed-by.ansi-neta-mts | Bushing Power Factor and Capacitance is addressed in ANSI/NETA MTS-2023. |
| tests.bushing-power-factor-and-capacitance.title | The test method is named Bushing Power Factor and Capacitance. Value: Bushing Power Factor and Capacitance. |
Cable Jacket Integrity
| Record | Statement |
|---|---|
| tests.cable-jacket-integrity.equipment.cable.acceptance | Cable Jacket Integrity is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3.B.4 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.cable-jacket-integrity.equipment.cable.maintenance | Cable Jacket Integrity is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.4 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.cable-jacket-integrity.governed-by.ansi-neta-ats | Cable Jacket Integrity is addressed in ANSI/NETA ATS-2025. |
| tests.cable-jacket-integrity.governed-by.ansi-neta-mts | Cable Jacket Integrity is addressed in ANSI/NETA MTS-2023. |
| tests.cable-jacket-integrity.title | The test method is named Cable Jacket Integrity. Value: Cable Jacket Integrity. |
Cable Tan Delta
| Record | Statement |
|---|---|
| tests.cable-tan-delta.equipment.cable.acceptance | Cable Tan Delta is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3.B.6 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.cable-tan-delta.equipment.cable.maintenance | Cable Tan Delta is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.7 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.cable-tan-delta.governed-by.ansi-neta-ats | Cable Tan Delta is addressed in ANSI/NETA ATS-2025. |
| tests.cable-tan-delta.governed-by.ansi-neta-mts | Cable Tan Delta is addressed in ANSI/NETA MTS-2023. |
| tests.cable-tan-delta.title | The test method is named Cable Tan Delta. Value: Cable Tan Delta. |
Capacitance Measurement
| Record | Statement |
|---|---|
| tests.capacitance-measurement.equipment.capacitor.acceptance | Capacitance Measurement is specified for capacitors in acceptance testing at clause 7.20.1.B.3 of ANSI/NETA ATS-2025. Value: capacitors. |
| tests.capacitance-measurement.equipment.capacitor.maintenance | Capacitance Measurement is specified for capacitors in maintenance testing at clause 7.20.1.B.3 of ANSI/NETA MTS-2023. Value: capacitors. |
| tests.capacitance-measurement.governed-by.ansi-neta-ats | Capacitance Measurement is addressed in ANSI/NETA ATS-2025. |
| tests.capacitance-measurement.governed-by.ansi-neta-mts | Capacitance Measurement is addressed in ANSI/NETA MTS-2023. |
| tests.capacitance-measurement.title | The test method is named Capacitance Measurement. Value: Capacitance Measurement. |
Constant Current Regulator Output
| Record | Statement |
|---|---|
| tests.constant-current-regulator-output.governed-by.faa-ac-150-5345-10h | Constant Current Regulator Output is addressed in FAA AC 150/5345-10H. |
| tests.constant-current-regulator-output.title | The test method is named Constant Current Regulator Output. Value: Constant Current Regulator Output. |
Contact Resistance
| Record | Statement |
|---|---|
| tests.contact-resistance.equipment.ats-transfer.acceptance | Contact Resistance is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.B.4 of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.contact-resistance.equipment.ats-transfer.maintenance | Contact Resistance is specified for automatic transfer switches in emergency systems in maintenance testing at clause 7.22.3.B.3 of ANSI/NETA MTS-2023. Value: automatic transfer switches in emergency systems. |
| tests.contact-resistance.equipment.network-protector.acceptance | Contact Resistance is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.3 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.contact-resistance.equipment.network-protector.maintenance | Contact Resistance is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.3 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.contact-resistance.equipment.sectionalizer.acceptance | Contact Resistance is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.3 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.contact-resistance.equipment.sectionalizer.maintenance | Contact Resistance is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.3 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.contact-resistance.governed-by.ansi-neta-ats | Contact Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.contact-resistance.governed-by.ansi-neta-mts | Contact Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.contact-resistance.title | The test method is named Contact Resistance. Value: Contact Resistance. |
Continuity and Shield Continuity
| Record | Statement |
|---|---|
| tests.continuity-and-shield-continuity.equipment.cable.acceptance | Continuity and Shield Continuity is specified for low-voltage cables in acceptance testing at clause 7.3.2.B.2 of ANSI/NETA ATS-2025. Value: low-voltage cables. |
| tests.continuity-and-shield-continuity.equipment.cable.maintenance | Continuity and Shield Continuity is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.3 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.continuity-and-shield-continuity.governed-by.ansi-neta-ats | Continuity and Shield Continuity is addressed in ANSI/NETA ATS-2025. |
| tests.continuity-and-shield-continuity.governed-by.ansi-neta-mts | Continuity and Shield Continuity is addressed in ANSI/NETA MTS-2023. |
| tests.continuity-and-shield-continuity.title | The test method is named Continuity and Shield Continuity. Value: Continuity and Shield Continuity. |
Control and Functional Verification
| Record | Statement |
|---|---|
| tests.control-and-functional-verification.equipment.ats-transfer.acceptance | Control and Functional Verification is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.B.5 of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.control-and-functional-verification.equipment.ats-transfer.maintenance | Control and Functional Verification is specified for automatic transfer switches in emergency systems in maintenance testing at clause 7.22.3.B.4 of ANSI/NETA MTS-2023. Value: automatic transfer switches in emergency systems. |
| tests.control-and-functional-verification.equipment.busway.acceptance | Control and Functional Verification is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.6 of ANSI/NETA ATS-2025. Value: metal-enclosed busways. |
| tests.control-and-functional-verification.equipment.busway.maintenance | Control and Functional Verification is specified for metal-enclosed busways in maintenance testing at clause 7.4.B.6 of ANSI/NETA MTS-2023. Value: metal-enclosed busways. |
| tests.control-and-functional-verification.equipment.commissioning-system.commissioning | Control and Functional Verification is specified for low-voltage systems in commissioning testing at clause 7.1.A.30 of ANSI/NETA ECS-2024. The pre-energization clause calls for the operation of transfer schemes to be verified. Value: low-voltage systems. |
| tests.control-and-functional-verification.equipment.drive.acceptance | Control and Functional Verification is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.B.7 of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.control-and-functional-verification.equipment.drive.maintenance | Control and Functional Verification is specified for adjustable-speed drive systems in maintenance testing at clause 7.17.B.7 of ANSI/NETA MTS-2023. Value: adjustable-speed drive systems. |
| tests.control-and-functional-verification.equipment.network-protector.acceptance | Control and Functional Verification is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.11 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.control-and-functional-verification.equipment.network-protector.maintenance | Control and Functional Verification is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.11 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.control-and-functional-verification.equipment.ups.acceptance | Control and Functional Verification is specified for uninterruptible power systems in acceptance testing at clause 7.22.2.B.5 of ANSI/NETA ATS-2025. Value: uninterruptible power systems. |
| tests.control-and-functional-verification.equipment.ups.maintenance | Control and Functional Verification is specified for uninterruptible power systems in maintenance testing at clause 7.22.2.B.5 of ANSI/NETA MTS-2023. Value: uninterruptible power systems. |
| tests.control-and-functional-verification.governed-by.ansi-neta-ats | Control and Functional Verification is addressed in ANSI/NETA ATS-2025. |
| tests.control-and-functional-verification.governed-by.ansi-neta-mts | Control and Functional Verification is addressed in ANSI/NETA MTS-2023. |
| tests.control-and-functional-verification.governed-by.faa-ac-150-5345-10h | Control and Functional Verification is addressed in FAA AC 150/5345-10H. |
| tests.control-and-functional-verification.title | The test method is named Control and Functional Verification. Value: Control and Functional Verification. |
Current Circuit Injection
| Record | Statement |
|---|---|
| tests.current-circuit-injection.equipment.commissioning-mv.commissioning | Current Circuit Injection is specified for medium-voltage systems in commissioning testing at clause 7.2.A.34 of ANSI/NETA ECS-2024. The pre-energization clause calls for system primary injection (through-fault) testing in accordance with the owner's project requirements. Value: medium-voltage systems. |
| tests.current-circuit-injection.governed-by.ansi-neta-ats | Current Circuit Injection is addressed in ANSI/NETA ATS-2025. |
| tests.current-circuit-injection.governed-by.ansi-neta-mts | Current Circuit Injection is addressed in ANSI/NETA MTS-2023. |
| tests.current-circuit-injection.title | The test method is named Current Circuit Injection. Value: Current Circuit Injection. |
DC System Ground Detection
| Record | Statement |
|---|---|
| tests.dc-system-ground-detection.equipment.solar.acceptance | DC System Ground Detection is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.8 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.dc-system-ground-detection.governed-by.ansi-neta-ats | DC System Ground Detection is addressed in ANSI/NETA ATS-2025. |
| tests.dc-system-ground-detection.governed-by.ansi-neta-mts | DC System Ground Detection is addressed in ANSI/NETA MTS-2023. |
| tests.dc-system-ground-detection.governed-by.ieee-946 | DC System Ground Detection is addressed in IEEE 946-2020. |
| tests.dc-system-ground-detection.title | The test method is named DC System Ground Detection. Value: DC System Ground Detection. |
Dielectric Frequency Response
| Record | Statement |
|---|---|
| tests.dielectric-frequency-response.governed-by.ansi-neta-ats | Dielectric Frequency Response is addressed in ANSI/NETA ATS-2025. |
| tests.dielectric-frequency-response.governed-by.ansi-neta-mts | Dielectric Frequency Response is addressed in ANSI/NETA MTS-2023. |
| tests.dielectric-frequency-response.title | The test method is named Dielectric Frequency Response. Value: Dielectric Frequency Response. |
Dielectric Withstand
| Record | Statement |
|---|---|
| tests.dielectric-withstand.equipment.busway-enclosed.acceptance | Dielectric Withstand is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.3 of ANSI/NETA ATS-2025. The clause calls for a dielectric withstand voltage test on each busway, phase-to-ground with the phases not under test grounded, at the manufacturer's test voltage. Value: metal-enclosed busways. |
| tests.dielectric-withstand.equipment.busway.acceptance | Dielectric Withstand is specified for outdoor bus structures in acceptance testing at clause 7.21.B.3 of ANSI/NETA ATS-2025. Value: outdoor bus structures. |
| tests.dielectric-withstand.equipment.busway.maintenance | Dielectric Withstand is specified for outdoor bus structures in maintenance testing at clause 7.21.B.3 of ANSI/NETA MTS-2023. Value: outdoor bus structures. |
| tests.dielectric-withstand.equipment.cable.acceptance | Dielectric Withstand is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.dielectric-withstand.equipment.cable.maintenance | Dielectric Withstand is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.6 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.dielectric-withstand.equipment.reactor.acceptance | Dielectric Withstand is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.4 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.dielectric-withstand.equipment.reactor.maintenance | Dielectric Withstand is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.4 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.dielectric-withstand.equipment.sectionalizer.acceptance | Dielectric Withstand is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.5 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.dielectric-withstand.equipment.sectionalizer.maintenance | Dielectric Withstand is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.5 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.dielectric-withstand.governed-by.ansi-neta-ats | Dielectric Withstand is addressed in ANSI/NETA ATS-2025. |
| tests.dielectric-withstand.governed-by.ansi-neta-mts | Dielectric Withstand is addressed in ANSI/NETA MTS-2023. |
| tests.dielectric-withstand.governed-by.faa-ac-150-5345-10h | Dielectric Withstand is addressed in FAA AC 150/5345-10H. |
| tests.dielectric-withstand.governed-by.ieee-c57-12-91 | Dielectric Withstand is addressed in IEEE C57.12.91-2020. |
| tests.dielectric-withstand.ieeec57-12-90.applied-voltage | Clause 10.6 of IEEE C57.12.90-2021 performs the applied-voltage test with every part of the winding under test connected to the line terminal and all other windings, the core and the tank grounded; the voltage is raised gradually from a low fraction of the test level, held for the stated duration and brought down gradually, and a failure shows as smoke or bubbling in the liquid, a thump inside the tank, or a test current that rises suddenly. |
| tests.dielectric-withstand.ieeec57-12-90.field | Clause 10.1.7 of IEEE C57.12.90-2021 is the one clause of the code that addresses testing in the field: periodic dielectric tests are not recommended because of the severity of the stress, they may be warranted after combustible gas detection or similar findings, and when required they are low-frequency applied-voltage and induced-voltage tests at reduced levels, with the voltage caps by transformer class and the durations given in the clause and in Table 2. |
| tests.dielectric-withstand.ieeec57-12-90.induced-voltage | Clauses 10.7 and 10.8 of IEEE C57.12.90-2021 perform the induced-voltage test by exciting the transformer at a raised frequency so that the core does not saturate, for a duration stated in cycles or time, with the Class II procedure adding an enhancement level followed by a lower level held for an extended period during which partial discharge is read at intervals and judged against the magnitude, rise and trend criteria of clause 10.8.5. |
| tests.dielectric-withstand.title | The test method is named Dielectric Withstand. Value: Dielectric Withstand. |
EMF Survey
| Record | Statement |
|---|---|
| tests.emf-survey.governed-by.ansi-neta-ats | EMF Survey is addressed in ANSI/NETA ATS-2025. |
| tests.emf-survey.governed-by.ansi-neta-mts | EMF Survey is addressed in ANSI/NETA MTS-2023. |
| tests.emf-survey.title | The test method is named EMF Survey. Value: EMF Survey. |
Energization Checks
| Record | Statement |
|---|---|
| tests.energization-checks.equipment.ats-transfer.commissioning | Energization Checks is specified for automatic transfer switches in commissioning testing at clause 8.3.A of ANSI/NETA ECS-2024. Value: automatic transfer switches. |
| tests.energization-checks.equipment.commissioning-hv.commissioning | Energization Checks is specified for high-voltage and extra-high-voltage systems in commissioning testing at clause 7.3.B.5 of ANSI/NETA ECS-2024. The energization clause calls for the steps of the written energization plan to be followed and documented. Value: high-voltage and extra-high-voltage systems. |
| tests.energization-checks.equipment.commissioning-mv.commissioning | Energization Checks is specified for medium-voltage systems in commissioning testing at clause 7.2.B.6 of ANSI/NETA ECS-2024. The energization clause calls for the steps of the written energization plan to be followed and documented. Value: medium-voltage systems. |
| tests.energization-checks.equipment.commissioning-system.commissioning | Energization Checks is specified for low-voltage systems in commissioning testing at clause 7.1.A of ANSI/NETA ECS-2024. Value: low-voltage systems. |
| tests.energization-checks.equipment.solar.commissioning | Energization Checks is specified for solar photovoltaic systems in commissioning testing at clause 8.1.A of ANSI/NETA ECS-2024. Value: solar photovoltaic systems. |
| tests.energization-checks.equipment.ups.commissioning | Energization Checks is specified for uninterruptible power supply systems in commissioning testing at clause 8.2.A of ANSI/NETA ECS-2024. Value: uninterruptible power supply systems. |
| tests.energization-checks.governed-by.ansi-neta-ecs | Energization Checks is addressed in ANSI/NETA ECS-2024. |
| tests.energization-checks.ieee1547-1.enter-service-checks | The on-off commissioning test of clause 8.2.3.1 in IEEE 1547.1-2020 verifies that the DER does not enter service while the permit signal is disabled, that it enters service with the permit enabled only when voltage and frequency are inside the enter-service window of IEEE 1547-2018, and that once voltage and frequency have returned the DER waits out the enter-service delay before reconnecting. |
| tests.energization-checks.ieee1547-1.installation-evaluation | Installation evaluation IE1 in clause 8.2.2.1 of IEEE 1547.1-2020 checks that the installation is complete, that the equipment nameplates match the design evaluation, that the installation follows the submitted electrical design, that grounding follows the interconnection agreement, that the isolation device has been visually inspected and operated, and that corrective actions are complete. |
| tests.energization-checks.ieee1547-1.settings-verification | Installation evaluation IE2 in clause 8.2.2.2 of IEEE 1547.1-2020 is run with the control system energized: the interconnection settings identified in the design evaluation are read, compared with the manufacturer's production report and checked against every setting the Area EPS operator requires, with the criterion that the actual settings match the project documentation. |
| tests.energization-checks.ieee1547.enter-service | Clause 4.10 of IEEE 1547-2018 permits a DER to begin service only if permit service is enabled and the applicable voltage and frequency fall within the windows of Table 4, and then only after an intentional minimum delay, with active power rising linearly or in steps at a rate the clause bounds; clause 6.6 applies the same criteria to return to service after a trip. |
| tests.energization-checks.title | The test method is named Energization Checks. Value: Energization Checks. |
Engine Generator Load and Performance
| Record | Statement |
|---|---|
| tests.engine-generator-load-and-performance.equipment.generator.acceptance | Engine Generator Load and Performance is specified for engine-generator emergency systems in acceptance testing at clause 7.22.1.B.6 of ANSI/NETA ATS-2025. Value: engine-generator emergency systems. |
| tests.engine-generator-load-and-performance.equipment.generator.maintenance | Engine Generator Load and Performance is specified for engine-generator emergency systems in maintenance testing at clause 7.22.1.B.5 of ANSI/NETA MTS-2023. Value: engine-generator emergency systems. |
| tests.engine-generator-load-and-performance.governed-by.ansi-neta-ats | Engine Generator Load and Performance is addressed in ANSI/NETA ATS-2025. |
| tests.engine-generator-load-and-performance.governed-by.ansi-neta-mts | Engine Generator Load and Performance is addressed in ANSI/NETA MTS-2023. |
| tests.engine-generator-load-and-performance.title | The test method is named Engine Generator Load and Performance. Value: Engine Generator Load and Performance. |
Engine Generator Safety Shutdowns
| Record | Statement |
|---|---|
| tests.engine-generator-safety-shutdowns.equipment.generator.acceptance | Engine Generator Safety Shutdowns is specified for engine-generator emergency systems in acceptance testing at clause 7.22.1 of ANSI/NETA ATS-2025. Value: engine-generator emergency systems. |
| tests.engine-generator-safety-shutdowns.equipment.generator.maintenance | Engine Generator Safety Shutdowns is specified for engine-generator emergency systems in maintenance testing at clause 7.22.1.B.3 of ANSI/NETA MTS-2023. Value: engine-generator emergency systems. |
| tests.engine-generator-safety-shutdowns.governed-by.ansi-neta-ats | Engine Generator Safety Shutdowns is addressed in ANSI/NETA ATS-2025. |
| tests.engine-generator-safety-shutdowns.governed-by.ansi-neta-mts | Engine Generator Safety Shutdowns is addressed in ANSI/NETA MTS-2023. |
| tests.engine-generator-safety-shutdowns.title | The test method is named Engine Generator Safety Shutdowns. Value: Engine Generator Safety Shutdowns. |
Fuse Resistance
| Record | Statement |
|---|---|
| tests.fuse-resistance.equipment.drive.acceptance | Fuse Resistance is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.B.9 of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.fuse-resistance.equipment.network-protector.acceptance | Fuse Resistance is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.6 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.fuse-resistance.equipment.network-protector.maintenance | Fuse Resistance is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.6 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.fuse-resistance.governed-by.ansi-neta-ats | Fuse Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.fuse-resistance.governed-by.ansi-neta-mts | Fuse Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.fuse-resistance.title | The test method is named Fuse Resistance. Value: Fuse Resistance. |
Ground Fault Protection Performance
| Record | Statement |
|---|---|
| tests.ground-fault-protection-performance.governed-by.ansi-neta-ats | Ground Fault Protection Performance is addressed in ANSI/NETA ATS-2025. |
| tests.ground-fault-protection-performance.governed-by.ansi-neta-mts | Ground Fault Protection Performance is addressed in ANSI/NETA MTS-2023. |
| tests.ground-fault-protection-performance.title | The test method is named Ground Fault Protection Performance. Value: Ground Fault Protection Performance. |
Infrared Thermographic Survey
| Record | Statement |
|---|---|
| tests.infrared-thermographic-survey.equipment.thermographic.acceptance | Infrared Thermographic Survey is specified for equipment surveyed by infrared thermography in acceptance testing at clause 9 of ANSI/NETA ATS-2025. Value: equipment surveyed by infrared thermography. |
| tests.infrared-thermographic-survey.equipment.thermographic.commissioning | Infrared Thermographic Survey is specified for equipment surveyed by infrared thermography in commissioning testing at clause 9 of ANSI/NETA ECS-2024. Value: equipment surveyed by infrared thermography. |
| tests.infrared-thermographic-survey.governed-by.ansi-neta-ats | Infrared Thermographic Survey is addressed in ANSI/NETA ATS-2025. |
| tests.infrared-thermographic-survey.governed-by.ansi-neta-ecs | Infrared Thermographic Survey is addressed in ANSI/NETA ECS-2024. |
| tests.infrared-thermographic-survey.title | The test method is named Infrared Thermographic Survey. Value: Infrared Thermographic Survey. |
Insulation Power Factor Dissipation Factor
| Record | Statement |
|---|---|
| tests.insulation-power-factor-dissipation-factor.equipment.busway.acceptance | Insulation Power Factor Dissipation Factor is specified for outdoor bus structures in acceptance testing at clause 7.21.B.4 of ANSI/NETA ATS-2025. Value: outdoor bus structures. |
| tests.insulation-power-factor-dissipation-factor.equipment.busway.maintenance | Insulation Power Factor Dissipation Factor is specified for outdoor bus structures in maintenance testing at clause 7.21.B.4 of ANSI/NETA MTS-2023. Value: outdoor bus structures. |
| tests.insulation-power-factor-dissipation-factor.equipment.reactor.acceptance | Insulation Power Factor Dissipation Factor is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.5 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.insulation-power-factor-dissipation-factor.equipment.reactor.maintenance | Insulation Power Factor Dissipation Factor is specified for liquid-filled shunt and current-limiting reactors in maintenance testing at clause 7.20.3.2.B of ANSI/NETA MTS-2023. Value: liquid-filled shunt and current-limiting reactors. |
| tests.insulation-power-factor-dissipation-factor.equipment.sectionalizer.acceptance | Insulation Power Factor Dissipation Factor is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.9 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.insulation-power-factor-dissipation-factor.equipment.sectionalizer.maintenance | Insulation Power Factor Dissipation Factor is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.9 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.insulation-power-factor-dissipation-factor.governed-by.ansi-neta-ats | Insulation Power Factor Dissipation Factor is addressed in ANSI/NETA ATS-2025. |
| tests.insulation-power-factor-dissipation-factor.governed-by.ansi-neta-mts | Insulation Power Factor Dissipation Factor is addressed in ANSI/NETA MTS-2023. |
| tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.conditions | Clause 10.10 of IEEE C57.12.90-2021 runs the insulation power-factor test with all windings immersed and short-circuited and all bushings in place, inside a stated temperature band near room temperature with the top liquid temperature recorded, using a bridge or the volt-ampere-watt method at or near power frequency, at a test voltage capped at a fraction of the low-frequency test level or a fixed ceiling, whichever is lower. |
| tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.connections | Table 4 of IEEE C57.12.90-2021 lists the insulation power-factor test connections for two-winding and three-winding transformers, with and without a guard circuit, and its footnote treats permanently connected windings such as those of autotransformers and regulators as a single winding. |
| tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.definition | IEEE C57.12.90-2021 defines insulation power factor as the watts that the insulation dissipates divided by the volt-amperes applied to it, measured with a sinusoidal voltage under prescribed conditions, and states that the test applies to liquid-immersed distribution and power transformers of present-day design. |
| tests.insulation-power-factor-dissipation-factor.ieeec57-12-90.no-standard-values | Notes to Table 4 of IEEE C57.12.90-2021 explain why the code sets no standard insulation power-factor value for a liquid-immersed transformer: the quantity does not track dielectric withstand, its change with temperature is large and erratic, and it depends on the liquid and the materials used; the as-measured value is therefore reported together with the liquid temperature, the code advises against applying a temperature correction, and the factory reading becomes the baseline for later periodic comparisons. |
| tests.insulation-power-factor-dissipation-factor.title | The test method is named Insulation Power Factor Dissipation Factor. Value: Insulation Power Factor Dissipation Factor. |
Insulation Resistance
| Record | Statement |
|---|---|
| tests.insulation-resistance.ats-conversion | ANSI/NETA ATS-2025 Table 100.14 provides insulation resistance conversion factors for referring readings to a standard temperature. |
| tests.insulation-resistance.ats-table-general | ANSI/NETA ATS-2025 Table 100.1 gives insulation resistance test values for electrical apparatus and systems other than rotating machinery. |
| tests.insulation-resistance.ats-table-rotating | ANSI/NETA ATS-2025 Table 100.11 gives insulation resistance test values for rotating machinery, stated for a one-minute reading at a reference temperature. |
| tests.insulation-resistance.ats-table-transformer | ANSI/NETA ATS-2025 Table 100.5 addresses transformer insulation resistance in acceptance testing. |
| tests.insulation-resistance.constant-dc | IEEE 43-2013 describes the test as normally made at a constant direct voltage of negative polarity, a choice it links to the electroendosmosis effect. |
| tests.insulation-resistance.definition | IEEE 43-2013 treats insulation resistance as the quotient of a direct voltage applied across the insulation and the current that the voltage drives through it, read at a stated time after the voltage is applied. |
| tests.insulation-resistance.dew-point | IEEE 43-2013 notes that when a winding is at or below the dew point a film of moisture can form on it and lower both the insulation resistance and the polarization index. |
| tests.insulation-resistance.discharge | IEEE 43-2013 requires the winding to be discharged before the test and, afterward, grounded through a current-limiting resistor for a period that it relates to how long the voltage was applied. |
| tests.insulation-resistance.discharge-practice | IEEE 43-2013 calls for the winding to be discharged before the test and, afterward, grounded through a current-limiting resistor for a period that it relates to how long the voltage was applied. |
| tests.insulation-resistance.equipment.ats-transfer.acceptance | Insulation Resistance is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.B.2 of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.insulation-resistance.equipment.ats-transfer.maintenance | Insulation Resistance is specified for automatic transfer switches in emergency systems in maintenance testing at clause 7.22.3.B.2 of ANSI/NETA MTS-2023. Value: automatic transfer switches in emergency systems. |
| tests.insulation-resistance.equipment.busway-enclosed.acceptance | Insulation Resistance is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.2 of ANSI/NETA ATS-2025. The clause calls for a one-minute insulation resistance test on each busway, phase-to-phase and phase-to-ground, at the manufacturer's test voltage. Value: metal-enclosed busways. |
| tests.insulation-resistance.equipment.busway.acceptance | Insulation Resistance is specified for outdoor bus structures in acceptance testing at clause 7.21.B.2 of ANSI/NETA ATS-2025. Value: outdoor bus structures. |
| tests.insulation-resistance.equipment.busway.maintenance | Insulation Resistance is specified for outdoor bus structures in maintenance testing at clause 7.21.B.2 of ANSI/NETA MTS-2023. Value: outdoor bus structures. |
| tests.insulation-resistance.equipment.cable.acceptance | Insulation Resistance is specified for low-voltage cables in acceptance testing at clause 7.3.2.B.1 of ANSI/NETA ATS-2025. Value: low-voltage cables. |
| tests.insulation-resistance.equipment.cable.maintenance | Insulation Resistance is specified for low-voltage cables in maintenance testing at clause 7.3.2.B of ANSI/NETA MTS-2023. Value: low-voltage cables. |
| tests.insulation-resistance.equipment.capacitor.acceptance | Insulation Resistance is specified for capacitors in acceptance testing at clause 7.20.1.B.2 of ANSI/NETA ATS-2025. Value: capacitors. |
| tests.insulation-resistance.equipment.capacitor.maintenance | Insulation Resistance is specified for capacitors in maintenance testing at clause 7.20.1.B.2 of ANSI/NETA MTS-2023. Value: capacitors. |
| tests.insulation-resistance.equipment.drive.acceptance | Insulation Resistance is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.B.4 of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.insulation-resistance.equipment.drive.maintenance | Insulation Resistance is specified for adjustable-speed drive systems in maintenance testing at clause 7.17.B.4 of ANSI/NETA MTS-2023. Value: adjustable-speed drive systems. |
| tests.insulation-resistance.equipment.network-protector.acceptance | Insulation Resistance is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.2 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.insulation-resistance.equipment.network-protector.maintenance | Insulation Resistance is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.2 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.insulation-resistance.equipment.reactor.acceptance | Insulation Resistance is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.2 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.insulation-resistance.equipment.reactor.maintenance | Insulation Resistance is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.2 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.insulation-resistance.equipment.resistor.acceptance | Insulation Resistance is specified for resistors in acceptance testing at clause 7.20.4.B.2 of ANSI/NETA ATS-2025. Value: resistors. |
| tests.insulation-resistance.equipment.resistor.maintenance | Insulation Resistance is specified for resistors in maintenance testing at clause 7.20.4.B.2 of ANSI/NETA MTS-2023. Value: resistors. |
| tests.insulation-resistance.equipment.sectionalizer.acceptance | Insulation Resistance is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.2 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.insulation-resistance.equipment.sectionalizer.maintenance | Insulation Resistance is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.2 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.insulation-resistance.equipment.solar.acceptance | Insulation Resistance is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.3 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.insulation-resistance.equipment.surge.acceptance | Insulation Resistance is specified for medium-voltage and high-voltage surge arresters in acceptance testing at clause 7.19.2.B.2 of ANSI/NETA ATS-2025. Value: medium-voltage and high-voltage surge arresters. |
| tests.insulation-resistance.equipment.surge.maintenance | Insulation Resistance is specified for low-voltage surge protective devices in maintenance testing at clause 7.19.1.B.2 of ANSI/NETA MTS-2023. Value: low-voltage surge protective devices. |
| tests.insulation-resistance.external-equipment | IEEE 43-2013 has cables, surge arresters, capacitors, voltage transformers and similar external equipment disconnected from the winding and grounded before the test, with any item left connected noted in the record. |
| tests.insulation-resistance.governed-by.ansi-neta-ats | Insulation Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.insulation-resistance.governed-by.ansi-neta-mts | Insulation Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.insulation-resistance.governed-by.ieee-43 | Insulation Resistance is addressed in IEEE 43-2013. |
| tests.insulation-resistance.governed-by.ieee-c57-13-1 | Insulation Resistance is addressed in IEEE C57.13.1-2017. |
| tests.insulation-resistance.governed-by.ieee-c57-15 | Insulation Resistance is addressed in IEEE/IEC C57.15-2017. |
| tests.insulation-resistance.governed-by.ieee-c57-18-10 | Insulation Resistance is addressed in IEEE C57.18.10-2021. |
| tests.insulation-resistance.ieeec57-12-90.procedure | Clause 10.11 of IEEE C57.12.90-2021 tests insulation resistance with the windings immersed, short-circuited and fitted with their bushings; circuits at the same voltage above ground are connected together while groups at different voltages are tested one at a time, the direct voltage is raised in increments with a hold at each step while the current is read, the test stops at once if the current keeps rising instead of settling, the direct voltage to ground stays within the low-frequency applied-voltage level of clause 10.6, and every terminal is grounded afterward until the trapped charge has drained. |
| tests.insulation-resistance.ieeec57-12-90.scope | Clause 10.11 of IEEE C57.12.90-2021 makes insulation resistance a test performed when specified, measured from each winding to ground and between windings, and reported in megohms or calculated from the applied voltage and the leakage current. |
| tests.insulation-resistance.ieeec57-12-90.significance | The notes to clause 10.11 of IEEE C57.12.90-2021 caution that an insulation-resistance reading is a weak indicator next to a dielectric-strength test, because design, temperature, moisture and surface cleanliness all move it, and give it two uses: a periodic trend plotted from readings taken at the same test voltage, and a check of whether a dielectric test can safely be applied; a reading is never taken with the tank under vacuum. The clause supplies neither a minimum megohm figure, nor a polarization index, nor a table of temperature corrections. |
| tests.insulation-resistance.limitations | IEEE 43-2013 notes that insulation resistance does not measure dielectric strength and that a test at standstill can miss internal voids and looseness that only rotation reveals. |
| tests.insulation-resistance.megohm-unit | IEEE 43-2013 expresses insulation resistance in megohms. |
| tests.insulation-resistance.minimum-values-shape | Clause 12.3 of IEEE 43-2013 recommends minimum one-minute insulation resistance values that depend on the type and construction of the winding and apply to the whole winding after correction to the reference temperature. |
| tests.insulation-resistance.mts-tables | ANSI/NETA MTS-2023 carries maintenance counterparts of the acceptance tables, including Table 100.1 for apparatus other than rotating machinery and Table 100.5 for transformer insulation resistance in maintenance testing. |
| tests.insulation-resistance.one-minute-reading | Under IEEE 43-2013 the reference insulation resistance reading is the one taken when the test voltage has been applied for one minute. Value: 1 min. |
| tests.insulation-resistance.osha-deenergize | Under 29 CFR 1910.333(a)(1), live parts to which an employee may be exposed are to be deenergized before the employee works on or near them, unless the employer shows that deenergizing creates added hazards or is infeasible. |
| tests.insulation-resistance.osha-insulated | 29 CFR 1910.399 defines insulated as separated from other conducting surfaces by a dielectric, including an air space, that offers a high resistance to the passage of current. |
| tests.insulation-resistance.osha-verify | Under 29 CFR 1910.333(b)(2)(iv)(B), a qualified person uses test equipment to verify that the circuit elements and electrical parts to be worked on are deenergized before they are treated as such. |
| tests.insulation-resistance.phase-connection | Where the winding allows it, IEEE 43-2013 favors testing each phase on its own with the other phases grounded to the core, and notes that a test of all phases together examines only the insulation to ground. |
| tests.insulation-resistance.purpose-ieee43 | IEEE 43-2013 states that it sets out to define the insulation resistance and polarization index tests, identify the factors that change the readings, recommend uniform test conditions and give a basis for interpreting the results. |
| tests.insulation-resistance.records | IEEE 43-2013 lists what is recorded with each test, among them the winding temperature, the temperature, humidity and dew point of the surrounding air, how long the machine has been out of service, the voltage applied and how the winding was connected. |
| tests.insulation-resistance.scope-machines | IEEE 43-2013 covers the armature and field windings of rotating machines, among them synchronous machines, induction machines, direct-current machines and synchronous condensers, and leaves fractional-horsepower machines out of its scope. |
| tests.insulation-resistance.small-current | IEEE 43-2013 notes that in insulation with a very high resistance the measured current is below a microampere. |
| tests.insulation-resistance.surface-moisture | Surface contamination, and insulating materials that take up moisture, lower the insulation resistance, and IEEE 43-2013 notes that cleaning and drying can bring it back up. |
| tests.insulation-resistance.temperature | Insulation resistance varies strongly with winding temperature, and IEEE 43-2013 gives a method for referring readings taken at different temperatures to one reference temperature. |
| tests.insulation-resistance.test-voltage-selection | IEEE 43-2013 ties the recommended direct test voltage to the rated voltage of the winding being tested. |
| tests.insulation-resistance.title | The test method is named Insulation Resistance. Value: Insulation Resistance. |
| tests.insulation-resistance.trend-indicators | IEEE 43-2013 reads a sharp fall in insulation resistance between successive tests as a sign of contamination, absorbed moisture or cracked insulation. |
| tests.insulation-resistance.trending-conditions | IEEE 43-2013 compares readings over time only when the tests were made at similar winding temperature, test voltage, duration and humidity, with the readings brought to a common temperature. |
| tests.insulation-resistance.voltage-application | IEEE 43-2013 brings the test voltage to its full value as quickly as practical and keeps it constant for the whole measurement. |
| tests.insulation-resistance.voltage-dependence | IEEE 43-2013 observes that dry insulation in good condition shows nearly the same insulation resistance as the test voltage is raised, while a marked fall with rising voltage points to a defect. |
Motor Overload Relay Trip
| Record | Statement |
|---|---|
| tests.motor-overload-relay-trip.equipment.drive.acceptance | Motor Overload Relay Trip is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.B.2 of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.motor-overload-relay-trip.equipment.drive.maintenance | Motor Overload Relay Trip is specified for adjustable-speed drive systems in maintenance testing at clause 7.17.B.2 of ANSI/NETA MTS-2023. Value: adjustable-speed drive systems. |
| tests.motor-overload-relay-trip.governed-by.ansi-neta-ats | Motor Overload Relay Trip is addressed in ANSI/NETA ATS-2025. |
| tests.motor-overload-relay-trip.governed-by.ansi-neta-mts | Motor Overload Relay Trip is addressed in ANSI/NETA MTS-2023. |
| tests.motor-overload-relay-trip.title | The test method is named Motor Overload Relay Trip. Value: Motor Overload Relay Trip. |
Network Protector Mechanism Tests
| Record | Statement |
|---|---|
| tests.network-protector-mechanism-tests.equipment.network-protector.acceptance | Network Protector Mechanism Tests is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.7 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.network-protector-mechanism-tests.equipment.network-protector.maintenance | Network Protector Mechanism Tests is specified for low-voltage network protectors in maintenance testing at clause 7.8.B.7 of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.network-protector-mechanism-tests.equipment.sectionalizer.acceptance | Network Protector Mechanism Tests is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.8 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.network-protector-mechanism-tests.equipment.sectionalizer.maintenance | Network Protector Mechanism Tests is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.8 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.network-protector-mechanism-tests.governed-by.ansi-neta-ats | Network Protector Mechanism Tests is addressed in ANSI/NETA ATS-2025. |
| tests.network-protector-mechanism-tests.governed-by.ansi-neta-mts | Network Protector Mechanism Tests is addressed in ANSI/NETA MTS-2023. |
| tests.network-protector-mechanism-tests.title | The test method is named Network Protector Mechanism Tests. Value: Network Protector Mechanism Tests. |
Partial Discharge Offline
| Record | Statement |
|---|---|
| tests.partial-discharge-offline.equipment.cable.acceptance | Partial Discharge Offline is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3.B.8 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.partial-discharge-offline.equipment.cable.maintenance | Partial Discharge Offline is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.9 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.partial-discharge-offline.governed-by.ansi-neta-ats | Partial Discharge Offline is addressed in ANSI/NETA ATS-2025. |
| tests.partial-discharge-offline.governed-by.ansi-neta-mts | Partial Discharge Offline is addressed in ANSI/NETA MTS-2023. |
| tests.partial-discharge-offline.title | The test method is named Partial Discharge Offline. Value: Partial Discharge Offline. |
Partial Discharge Online
| Record | Statement |
|---|---|
| tests.partial-discharge-online.equipment.busway.acceptance | Partial Discharge Online is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.7 of ANSI/NETA ATS-2025. Value: metal-enclosed busways. |
| tests.partial-discharge-online.equipment.busway.maintenance | Partial Discharge Online is specified for metal-enclosed busways in maintenance testing at clause 7.4.B.7 of ANSI/NETA MTS-2023. Value: metal-enclosed busways. |
| tests.partial-discharge-online.equipment.cable.acceptance | Partial Discharge Online is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3.B.7 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.partial-discharge-online.equipment.cable.maintenance | Partial Discharge Online is specified for shielded medium-voltage and high-voltage cables in maintenance testing at clause 7.3.3.B.8 of ANSI/NETA MTS-2023. Value: shielded medium-voltage and high-voltage cables. |
| tests.partial-discharge-online.equipment.partialdischarge.acceptance | Partial Discharge Online is specified for equipment surveyed for online partial discharge in acceptance testing at clause 11 of ANSI/NETA ATS-2025. Value: equipment surveyed for online partial discharge. |
| tests.partial-discharge-online.equipment.reactor.maintenance | Partial Discharge Online is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.5 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.partial-discharge-online.governed-by.ansi-neta-ats | Partial Discharge Online is addressed in ANSI/NETA ATS-2025. |
| tests.partial-discharge-online.governed-by.ansi-neta-mts | Partial Discharge Online is addressed in ANSI/NETA MTS-2023. |
| tests.partial-discharge-online.title | The test method is named Partial Discharge Online. Value: Partial Discharge Online. |
Phase Rotation and Phasing
| Record | Statement |
|---|---|
| tests.phase-rotation-and-phasing.equipment.ats-transfer.acceptance | Phase Rotation and Phasing is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.B.7 of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.phase-rotation-and-phasing.equipment.busway.acceptance | Phase Rotation and Phasing is specified for metal-enclosed busways in acceptance testing at clause 7.4.B.5 of ANSI/NETA ATS-2025. Value: metal-enclosed busways. |
| tests.phase-rotation-and-phasing.equipment.commissioning-mv.commissioning | Phase Rotation and Phasing is specified for medium-voltage systems in commissioning testing at clause 7.2.B.9 of ANSI/NETA ECS-2024. The energization clause calls for the equipment phasing to be verified. Value: medium-voltage systems. |
| tests.phase-rotation-and-phasing.equipment.commissioning-system.commissioning | Phase Rotation and Phasing is specified for low-voltage systems in commissioning testing at clause 7.1.B.9 of ANSI/NETA ECS-2024. The energization clause calls for the equipment phasing to be verified. Value: low-voltage systems. |
| tests.phase-rotation-and-phasing.equipment.network-protector.acceptance | Phase Rotation and Phasing is specified for low-voltage network protectors in acceptance testing at clause 7.8.B.12 of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.phase-rotation-and-phasing.equipment.ups.acceptance | Phase Rotation and Phasing is specified for uninterruptible power systems in acceptance testing at clause 7.22.2.B.6 of ANSI/NETA ATS-2025. Value: uninterruptible power systems. |
| tests.phase-rotation-and-phasing.equipment.ups.maintenance | Phase Rotation and Phasing is specified for uninterruptible power systems in maintenance testing at clause 7.22.2.B.6 of ANSI/NETA MTS-2023. Value: uninterruptible power systems. |
| tests.phase-rotation-and-phasing.governed-by.ansi-neta-ats | Phase Rotation and Phasing is addressed in ANSI/NETA ATS-2025. |
| tests.phase-rotation-and-phasing.governed-by.ansi-neta-mts | Phase Rotation and Phasing is addressed in ANSI/NETA MTS-2023. |
| tests.phase-rotation-and-phasing.ieee1547-1.synchronization-check | Commissioning test CT2 in clause 8.2.3.2 of IEEE 1547.1-2020 checks and records the phase rotation on both sides of the interconnection and, where a synchronizing relay is used, confirms that closure of the breaker is blocked outside the design limits; the criteria refer to the frequency, voltage and phase-angle difference limits of IEEE 1547-2018 Table 5 for synchronous DER and to the rapid voltage change limits at paralleling. |
| tests.phase-rotation-and-phasing.title | The test method is named Phase Rotation and Phasing. Value: Phase Rotation and Phasing. |
Polarity Test
| Record | Statement |
|---|---|
| tests.polarity-test.equipment.solar.acceptance | Polarity Test is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.1 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.polarity-test.governed-by.ansi-neta-ats | Polarity Test is addressed in ANSI/NETA ATS-2025. |
| tests.polarity-test.governed-by.ansi-neta-mts | Polarity Test is addressed in ANSI/NETA MTS-2023. |
| tests.polarity-test.governed-by.ieee-c57-13 | Polarity Test is addressed in IEEE C57.13-2016. |
| tests.polarity-test.governed-by.ieee-c57-13-1 | Polarity Test is addressed in IEEE C57.13.1-2017. |
| tests.polarity-test.ieeec57-12-90.methods | Clause 6.2 of IEEE C57.12.90-2021 determines single-phase polarity by the inductive kick method, by an alternating-voltage test, or by comparison with a transformer of known polarity. |
| tests.polarity-test.ieeec57-12-90.phase-relation | Clause 6.3 of IEEE C57.12.90-2021 determines the angular displacement and phase sequence of polyphase transformers by phasor-diagram methods; polarity and phase relation carry no tolerance, since the result either matches the nameplate or does not. |
| tests.polarity-test.title | The test method is named Polarity Test. Value: Polarity Test. |
Polarization Index and Dielectric Absorption
| Record | Statement |
|---|---|
| tests.polarization-index-and-dielectric-absorption.absorption-current | IEEE 43-2013 links the usefulness of the polarization index to the absorption current, the part of the measured current that dies away while the voltage is held, so the index loses its meaning where that current disappears within seconds. |
| tests.polarization-index-and-dielectric-absorption.annex-variants | Annex A of IEEE 43-2013 describes variants of the polarization index built on shorter reading times and states that no agreed pass or fail criteria exist for them. |
| tests.polarization-index-and-dielectric-absorption.ats-dar | ANSI/NETA ATS-2025 uses a dielectric absorption ratio for rotating machinery, a measure that IEEE 43-2013 describes only as an informative variant. |
| tests.polarization-index-and-dielectric-absorption.ats-rotating | ANSI/NETA ATS-2025 section 7.15.1 evaluates polarization index results for AC induction motors and generators in its own text, and its criteria do not coincide in every case with the minimums recommended in IEEE 43-2013. |
| tests.polarization-index-and-dielectric-absorption.both-minimums | IEEE 43-2013 expects a machine to clear both its polarization index and its one-minute insulation resistance recommendations before it is returned to operation or given an overvoltage test. |
| tests.polarization-index-and-dielectric-absorption.dar-thirty-second | One variant in Annex A of IEEE 43-2013 divides the one-minute insulation resistance by a reading taken thirty seconds after the voltage is applied. Value: 30 s. |
| tests.polarization-index-and-dielectric-absorption.drying | IEEE 43-2013 notes that the polarization index can indicate when the drying of a winding may be stopped. |
| tests.polarization-index-and-dielectric-absorption.equipment.reactor.acceptance | Polarization Index and Dielectric Absorption is specified for liquid-filled shunt and current-limiting reactors in acceptance testing at clause 7.20.3.2.B.2 of ANSI/NETA ATS-2025. Value: liquid-filled shunt and current-limiting reactors. |
| tests.polarization-index-and-dielectric-absorption.equipment.reactor.maintenance | Polarization Index and Dielectric Absorption is specified for liquid-filled shunt and current-limiting reactors in maintenance testing at clause 7.20.3.2.B of ANSI/NETA MTS-2023. Value: liquid-filled shunt and current-limiting reactors. |
| tests.polarization-index-and-dielectric-absorption.governed-by.ansi-neta-ats | Polarization Index and Dielectric Absorption is addressed in ANSI/NETA ATS-2025. |
| tests.polarization-index-and-dielectric-absorption.governed-by.ansi-neta-mts | Polarization Index and Dielectric Absorption is addressed in ANSI/NETA MTS-2023. |
| tests.polarization-index-and-dielectric-absorption.high-ir-disregard | When the one-minute insulation resistance at the reference temperature is very high, the measured current is so small that IEEE 43-2013 allows the polarization index to be disregarded. |
| tests.polarization-index-and-dielectric-absorption.intermediate-readings | IEEE 43-2013 notes that readings at several intervals during the test are commonly recorded so that resistance can be plotted against time. |
| tests.polarization-index-and-dielectric-absorption.minimum-shape | Clause 12.2 of IEEE 43-2013 recommends minimum polarization index values that depend on the thermal class of the insulation. |
| tests.polarization-index-and-dielectric-absorption.no-temperature-correction | IEEE 43-2013 applies no temperature correction to the polarization index, and it calls for a repeat test at a lower temperature when a hot winding that cooled during the test gives a high result. |
| tests.polarization-index-and-dielectric-absorption.not-applicable | IEEE 43-2013 does not apply the polarization index to non-insulated field windings, such as squirrel-cage rotor windings, or to direct-current armatures with exposed commutator copper. |
| tests.polarization-index-and-dielectric-absorption.pi-definition | IEEE 43-2013 defines the polarization index as the insulation resistance read after ten minutes of applied voltage divided by the insulation resistance read after one minute. |
| tests.polarization-index-and-dielectric-absorption.small-machines | IEEE 43-2013 regards the polarization index as not meaningful for small random-wound machines, because their absorption current dies away within a few seconds. |
| tests.polarization-index-and-dielectric-absorption.stress-control | IEEE 43-2013 notes that a continuous stress-control coating over the whole end-winding region can pull the polarization index toward unity. |
| tests.polarization-index-and-dielectric-absorption.ten-minute | The later of the two readings that make up the polarization index under IEEE 43-2013 is taken ten minutes after the test voltage is applied. Value: 10 min. |
| tests.polarization-index-and-dielectric-absorption.title | The test method is named Polarization Index and Dielectric Absorption. Value: Polarization Index and Dielectric Absorption. |
| tests.polarization-index-and-dielectric-absorption.trend-fall | IEEE 43-2013 reads a sharp fall in the polarization index between tests, like a sharp fall in the one-minute insulation resistance, as a sign of contamination, moisture or cracked insulation. |
Power Factor Tip Up
| Record | Statement |
|---|---|
| tests.power-factor-tip-up.governed-by.ansi-neta-ats | Power Factor Tip Up is addressed in ANSI/NETA ATS-2025. |
| tests.power-factor-tip-up.governed-by.ansi-neta-mts | Power Factor Tip Up is addressed in ANSI/NETA MTS-2023. |
| tests.power-factor-tip-up.title | The test method is named Power Factor Tip Up. Value: Power Factor Tip Up. |
PV I-V Curve Tracing
| Record | Statement |
|---|---|
| tests.pv-iv-curve-tracing.equipment.solar.acceptance | PV I-V Curve Tracing is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.7 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.pv-iv-curve-tracing.governed-by.ansi-neta-ats | PV I-V Curve Tracing is addressed in ANSI/NETA ATS-2025. |
| tests.pv-iv-curve-tracing.title | The test method is named PV I-V Curve Tracing. Value: PV I-V Curve Tracing. |
PV String Voc and Isc
| Record | Statement |
|---|---|
| tests.pv-string-voc-and-isc.equipment.solar.acceptance | PV String Voc and Isc is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.2 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.pv-string-voc-and-isc.governed-by.ansi-neta-ats | PV String Voc and Isc is addressed in ANSI/NETA ATS-2025. |
| tests.pv-string-voc-and-isc.title | The test method is named PV String Voc and Isc. Value: PV String Voc and Isc. |
PV Wet Insulation Resistance
| Record | Statement |
|---|---|
| tests.pv-wet-insulation-resistance.equipment.solar.acceptance | PV Wet Insulation Resistance is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.4 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.pv-wet-insulation-resistance.governed-by.ansi-neta-ats | PV Wet Insulation Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.pv-wet-insulation-resistance.title | The test method is named PV Wet Insulation Resistance. Value: PV Wet Insulation Resistance. |
Recloser and Sectionalizer Operation
| Record | Statement |
|---|---|
| tests.recloser-and-sectionalizer-operation.equipment.sectionalizer.acceptance | Recloser and Sectionalizer Operation is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.B.6 of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.recloser-and-sectionalizer-operation.equipment.sectionalizer.maintenance | Recloser and Sectionalizer Operation is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.B.6 of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.recloser-and-sectionalizer-operation.governed-by.ansi-neta-ats | Recloser and Sectionalizer Operation is addressed in ANSI/NETA ATS-2025. |
| tests.recloser-and-sectionalizer-operation.governed-by.ansi-neta-mts | Recloser and Sectionalizer Operation is addressed in ANSI/NETA MTS-2023. |
| tests.recloser-and-sectionalizer-operation.title | The test method is named Recloser and Sectionalizer Operation. Value: Recloser and Sectionalizer Operation. |
Rectifier Converter Performance
| Record | Statement |
|---|---|
| tests.rectifier-converter-performance.governed-by.ieee-946 | Rectifier Converter Performance is addressed in IEEE 946-2020. |
| tests.rectifier-converter-performance.governed-by.ieee-c57-12-00 | Rectifier Converter Performance is addressed in IEEE C57.12.00-2021. |
| tests.rectifier-converter-performance.governed-by.ieee-c57-12-01 | Rectifier Converter Performance is addressed in IEEE C57.12.01-2020. |
| tests.rectifier-converter-performance.governed-by.ieee-c57-18-10 | Rectifier Converter Performance is addressed in IEEE C57.18.10-2021. |
| tests.rectifier-converter-performance.title | The test method is named Rectifier Converter Performance. Value: Rectifier Converter Performance. |
Resistor and Coil Resistance
| Record | Statement |
|---|---|
| tests.resistor-and-coil-resistance.equipment.cable.acceptance | Resistor and Coil Resistance is specified for low-voltage cables in acceptance testing at clause 7.3.2.B.3 of ANSI/NETA ATS-2025. Value: low-voltage cables. |
| tests.resistor-and-coil-resistance.equipment.cable.maintenance | Resistor and Coil Resistance is specified for low-voltage cables in maintenance testing at clause 7.3.2.B of ANSI/NETA MTS-2023. Value: low-voltage cables. |
| tests.resistor-and-coil-resistance.equipment.resistor.acceptance | Resistor and Coil Resistance is specified for resistors in acceptance testing at clause 7.20.4.B.3 of ANSI/NETA ATS-2025. Value: resistors. |
| tests.resistor-and-coil-resistance.equipment.resistor.maintenance | Resistor and Coil Resistance is specified for resistors in maintenance testing at clause 7.20.4.B.5 of ANSI/NETA MTS-2023. Value: resistors. |
| tests.resistor-and-coil-resistance.governed-by.ansi-neta-ats | Resistor and Coil Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.resistor-and-coil-resistance.governed-by.ansi-neta-mts | Resistor and Coil Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.resistor-and-coil-resistance.title | The test method is named Resistor and Coil Resistance. Value: Resistor and Coil Resistance. |
RTD Circuit Verification
| Record | Statement |
|---|---|
| tests.rtd-circuit-verification.governed-by.ansi-neta-ats | RTD Circuit Verification is addressed in ANSI/NETA ATS-2025. |
| tests.rtd-circuit-verification.governed-by.ansi-neta-mts | RTD Circuit Verification is addressed in ANSI/NETA MTS-2023. |
| tests.rtd-circuit-verification.title | The test method is named RTD Circuit Verification. Value: RTD Circuit Verification. |
SCADA and Communication Verification
| Record | Statement |
|---|---|
| tests.scada-and-communication-verification.equipment.commissioning-system.maintenance | SCADA and Communication Verification is specified for complete electrical systems in maintenance testing at clause 8 of ANSI/NETA MTS-2023. Value: complete electrical systems. |
| tests.scada-and-communication-verification.equipment.solar.acceptance | SCADA and Communication Verification is specified for solar photovoltaic systems in acceptance testing at clause 7.29.B.10 of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.scada-and-communication-verification.governed-by.ansi-neta-ats | SCADA and Communication Verification is addressed in ANSI/NETA ATS-2025. |
| tests.scada-and-communication-verification.governed-by.ansi-neta-mts | SCADA and Communication Verification is addressed in ANSI/NETA MTS-2023. |
| tests.scada-and-communication-verification.ieee2800.communication-interface | Clause 4.5 of IEEE 2800-2022 requires a secure bidirectional local communication interface at the plant, with protocols and data items set by the interconnection agreement and cyber security measures; Table 20 lists this capability among those verified by commissioning tests, and the method of verification is by mutual agreement. |
| tests.scada-and-communication-verification.title | The test method is named SCADA and Communication Verification. Value: SCADA and Communication Verification. |
SF6 Gas Quality
| Record | Statement |
|---|---|
| tests.sf6-gas-quality.governed-by.ansi-neta-ats | SF6 Gas Quality is addressed in ANSI/NETA ATS-2025. |
| tests.sf6-gas-quality.governed-by.ansi-neta-mts | SF6 Gas Quality is addressed in ANSI/NETA MTS-2023. |
| tests.sf6-gas-quality.title | The test method is named SF6 Gas Quality. Value: SF6 Gas Quality. |
Surge Arrester and SPD Tests
| Record | Statement |
|---|---|
| tests.surge-arrester-and-spd-tests.equipment.surge.acceptance | Surge Arrester and SPD Tests is specified for medium-voltage and high-voltage surge arresters in acceptance testing at clause 7.19.2.B.4 of ANSI/NETA ATS-2025. Value: medium-voltage and high-voltage surge arresters. |
| tests.surge-arrester-and-spd-tests.equipment.surge.maintenance | Surge Arrester and SPD Tests is specified for medium-voltage and high-voltage surge arresters in maintenance testing at clause 7.19.2.B of ANSI/NETA MTS-2023. Value: medium-voltage and high-voltage surge arresters. |
| tests.surge-arrester-and-spd-tests.governed-by.ansi-neta-ats | Surge Arrester and SPD Tests is addressed in ANSI/NETA ATS-2025. |
| tests.surge-arrester-and-spd-tests.governed-by.ansi-neta-mts | Surge Arrester and SPD Tests is addressed in ANSI/NETA MTS-2023. |
| tests.surge-arrester-and-spd-tests.title | The test method is named Surge Arrester and SPD Tests. Value: Surge Arrester and SPD Tests. |
System Function Testing
| Record | Statement |
|---|---|
| tests.system-function-testing.equipment.commissioning-system.acceptance | System Function Testing is specified for complete electrical systems in acceptance testing at clause 8 of ANSI/NETA ATS-2025. Value: complete electrical systems. |
| tests.system-function-testing.equipment.commissioning-system.maintenance | System Function Testing is specified for complete electrical systems in maintenance testing at clause 8 of ANSI/NETA MTS-2023. Value: complete electrical systems. |
| tests.system-function-testing.equipment.evcharging.acceptance | System Function Testing is specified for electric vehicle charging systems in acceptance testing at clause 7.26.B.1 of ANSI/NETA ATS-2025. Value: electric vehicle charging systems. |
| tests.system-function-testing.equipment.evcharging.maintenance | System Function Testing is specified for electric vehicle charging systems in maintenance testing at clause 7.26.B.2 of ANSI/NETA MTS-2023. Value: electric vehicle charging systems. |
| tests.system-function-testing.governed-by.ansi-neta-ats | System Function Testing is addressed in ANSI/NETA ATS-2025. |
| tests.system-function-testing.governed-by.ansi-neta-mts | System Function Testing is addressed in ANSI/NETA MTS-2023. |
| tests.system-function-testing.ieee1547-1.commissioning-scope | Table 71 in clause 8.1.3.4.1 of IEEE 1547.1-2020 distinguishes a basic commissioning test, which may consist of a visual inspection together with an operability check of the isolation device and whose scope the design evaluation sets, from a detailed commissioning test, which adds functional tests of the combined devices. |
| tests.system-function-testing.ieee1547-1.on-off-test | Commissioning test CT1 in clause 8.2.3.1 of IEEE 1547.1-2020 is an on-off test: the DER is brought online from off in the specified mode while the voltage response of the Area EPS, the intentional delay and the ramp to steady state are observed, a disconnect and reconnect are simulated, and cease to energize is verified when all ungrounded phases are opened by some device other than the interconnection device and, for multiphase DER, when one phase is opened at the PoC. Observations are reviewed with the Area EPS operator, results are documented with the agreement of both operators, and any failure carries agreed corrective action and a repeat of the test. |
| tests.system-function-testing.ieee1547-1.periodic-reverification | Under clause 9 of IEEE 1547.1-2020, periodic re-verification of a DER uses the clause 8 field methods as agreed between the operators, and the Area EPS operator receives documentation of the updated configuration together with the re-verification results. |
| tests.system-function-testing.ieee1547.commissioning-tests | Clause 11.2.5 of IEEE 1547-2018 requires DER commissioning tests to follow written procedures from the manufacturer or system designer that the owner and the area electric power system operator have approved, always to include a visual inspection, and distinguishes a basic commissioning test (visual inspection plus operability of the isolation device) from a detailed one that adds functional tests of the interconnection devices as a system. |
| tests.system-function-testing.ieee2800.commissioning-tests | Clause 12.2.5 of IEEE 2800-2022 defines a commissioning test as a field verification of a unit, a supplemental device or the whole plant, run in every case to a written procedure that follows good engineering practice and that the transmission system operator has accepted as suited to the requirement; such tests may include operability and functional performance tests. |
| tests.system-function-testing.title | The test method is named System Function Testing. Value: System Function Testing. |
Time Domain Reflectometry
| Record | Statement |
|---|---|
| tests.time-domain-reflectometry.equipment.cable.acceptance | Time Domain Reflectometry is specified for shielded medium-voltage and high-voltage cables in acceptance testing at clause 7.3.3.B.3 of ANSI/NETA ATS-2025. Value: shielded medium-voltage and high-voltage cables. |
| tests.time-domain-reflectometry.governed-by.ansi-neta-ats | Time Domain Reflectometry is addressed in ANSI/NETA ATS-2025. |
| tests.time-domain-reflectometry.title | The test method is named Time Domain Reflectometry. Value: Time Domain Reflectometry. |
UPS Functional and Transfer Tests
| Record | Statement |
|---|---|
| tests.ups-functional-and-transfer-tests.equipment.surge.acceptance | UPS Functional and Transfer Tests is specified for low-voltage surge protective devices in acceptance testing at clause 7.19.1.B.1 of ANSI/NETA ATS-2025. Value: low-voltage surge protective devices. |
| tests.ups-functional-and-transfer-tests.equipment.surge.maintenance | UPS Functional and Transfer Tests is specified for low-voltage surge protective devices in maintenance testing at clause 7.19.1.A.8 of ANSI/NETA MTS-2023. Value: low-voltage surge protective devices. |
| tests.ups-functional-and-transfer-tests.equipment.ups.acceptance | UPS Functional and Transfer Tests is specified for uninterruptible power systems in acceptance testing at clause 7.22.2.B.2 of ANSI/NETA ATS-2025. Value: uninterruptible power systems. |
| tests.ups-functional-and-transfer-tests.equipment.ups.maintenance | UPS Functional and Transfer Tests is specified for uninterruptible power systems in maintenance testing at clause 7.22.2.B.2 of ANSI/NETA MTS-2023. Value: uninterruptible power systems. |
| tests.ups-functional-and-transfer-tests.governed-by.ansi-neta-ats | UPS Functional and Transfer Tests is addressed in ANSI/NETA ATS-2025. |
| tests.ups-functional-and-transfer-tests.governed-by.ansi-neta-mts | UPS Functional and Transfer Tests is addressed in ANSI/NETA MTS-2023. |
| tests.ups-functional-and-transfer-tests.title | The test method is named UPS Functional and Transfer Tests. Value: UPS Functional and Transfer Tests. |
Vacuum Interrupter Integrity
| Record | Statement |
|---|---|
| tests.vacuum-interrupter-integrity.governed-by.ansi-neta-ats | Vacuum Interrupter Integrity is addressed in ANSI/NETA ATS-2025. |
| tests.vacuum-interrupter-integrity.governed-by.ansi-neta-mts | Vacuum Interrupter Integrity is addressed in ANSI/NETA MTS-2023. |
| tests.vacuum-interrupter-integrity.title | The test method is named Vacuum Interrupter Integrity. Value: Vacuum Interrupter Integrity. |
Vacuum Interrupter MAC Test
| Record | Statement |
|---|---|
| tests.vacuum-interrupter-mac-test.governed-by.ansi-neta-ats | Vacuum Interrupter MAC Test is addressed in ANSI/NETA ATS-2025. |
| tests.vacuum-interrupter-mac-test.governed-by.ansi-neta-mts | Vacuum Interrupter MAC Test is addressed in ANSI/NETA MTS-2023. |
| tests.vacuum-interrupter-mac-test.title | The test method is named Vacuum Interrupter MAC Test. Value: Vacuum Interrupter MAC Test. |
Visual and Mechanical Inspection
| Record | Statement |
|---|---|
| tests.visual-and-mechanical-inspection.equipment.arrester-mv-hv.maintenance | Visual and Mechanical Inspection is specified for medium-voltage and high-voltage surge arresters in maintenance testing at clause 7.19.2.A of ANSI/NETA MTS-2023. The clause covers the physical and mechanical condition, anchorage, alignment and grounding, cleaning, bolted connections, the ground lead of each device individually attached to a ground bus or ground electrode, and the mounting and electrical connection of a stroke counter where one is fitted, with as-found and as-left tests around the cleaning. Value: medium-voltage and high-voltage surge arresters. |
| tests.visual-and-mechanical-inspection.equipment.ats-transfer.acceptance | Visual and Mechanical Inspection is specified for automatic transfer switches in emergency systems in acceptance testing at clause 7.22.3.A of ANSI/NETA ATS-2025. Value: automatic transfer switches in emergency systems. |
| tests.visual-and-mechanical-inspection.equipment.ats-transfer.maintenance | Visual and Mechanical Inspection is specified for automatic transfer switches in emergency systems in maintenance testing at clause 7.22.3.A of ANSI/NETA MTS-2023. Value: automatic transfer switches in emergency systems. |
| tests.visual-and-mechanical-inspection.equipment.automation.acceptance | Visual and Mechanical Inspection is specified for automation and communication systems in acceptance testing at clause 7.23.A of ANSI/NETA ATS-2025. Value: automation and communication systems. |
| tests.visual-and-mechanical-inspection.equipment.automation.maintenance | Visual and Mechanical Inspection is specified for automation and communication systems in maintenance testing at clause 7.23.A of ANSI/NETA MTS-2023. Value: automation and communication systems. |
| tests.visual-and-mechanical-inspection.equipment.busway.acceptance | Visual and Mechanical Inspection is specified for outdoor bus structures in acceptance testing at clause 7.21.A of ANSI/NETA ATS-2025. Value: outdoor bus structures. |
| tests.visual-and-mechanical-inspection.equipment.busway.maintenance | Visual and Mechanical Inspection is specified for outdoor bus structures in maintenance testing at clause 7.21.A of ANSI/NETA MTS-2023. Value: outdoor bus structures. |
| tests.visual-and-mechanical-inspection.equipment.cable.acceptance | Visual and Mechanical Inspection is specified for fiber-optic cables in acceptance testing at clause 7.25.A of ANSI/NETA ATS-2025. Value: fiber-optic cables. |
| tests.visual-and-mechanical-inspection.equipment.cable.maintenance | Visual and Mechanical Inspection is specified for fiber-optic cables in maintenance testing at clause 7.25.A of ANSI/NETA MTS-2023. Value: fiber-optic cables. |
| tests.visual-and-mechanical-inspection.equipment.capacitor.acceptance | Visual and Mechanical Inspection is specified for capacitors in acceptance testing at clause 7.20.1.A of ANSI/NETA ATS-2025. Value: capacitors. |
| tests.visual-and-mechanical-inspection.equipment.capacitor.maintenance | Visual and Mechanical Inspection is specified for capacitors in maintenance testing at clause 7.20.1.A of ANSI/NETA MTS-2023. Value: capacitors. |
| tests.visual-and-mechanical-inspection.equipment.drive.acceptance | Visual and Mechanical Inspection is specified for adjustable-speed drive systems in acceptance testing at clause 7.17.A of ANSI/NETA ATS-2025. Value: adjustable-speed drive systems. |
| tests.visual-and-mechanical-inspection.equipment.drive.maintenance | Visual and Mechanical Inspection is specified for adjustable-speed drive systems in maintenance testing at clause 7.17.A of ANSI/NETA MTS-2023. Value: adjustable-speed drive systems. |
| tests.visual-and-mechanical-inspection.equipment.evcharging.acceptance | Visual and Mechanical Inspection is specified for electric vehicle charging systems in acceptance testing at clause 7.26.A of ANSI/NETA ATS-2025. Value: electric vehicle charging systems. |
| tests.visual-and-mechanical-inspection.equipment.evcharging.maintenance | Visual and Mechanical Inspection is specified for electric vehicle charging systems in maintenance testing at clause 7.26.A of ANSI/NETA MTS-2023. Value: electric vehicle charging systems. |
| tests.visual-and-mechanical-inspection.equipment.network-protector.acceptance | Visual and Mechanical Inspection is specified for low-voltage network protectors in acceptance testing at clause 7.8.A of ANSI/NETA ATS-2025. Value: low-voltage network protectors. |
| tests.visual-and-mechanical-inspection.equipment.network-protector.maintenance | Visual and Mechanical Inspection is specified for low-voltage network protectors in maintenance testing at clause 7.8.A of ANSI/NETA MTS-2023. Value: low-voltage network protectors. |
| tests.visual-and-mechanical-inspection.equipment.partialdischarge.maintenance | Visual and Mechanical Inspection is specified for equipment surveyed for online partial discharge in maintenance testing at clause 11 of ANSI/NETA MTS-2023. Value: equipment surveyed for online partial discharge. |
| tests.visual-and-mechanical-inspection.equipment.reactor.acceptance | Visual and Mechanical Inspection is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.A of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.visual-and-mechanical-inspection.equipment.reactor.maintenance | Visual and Mechanical Inspection is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.A of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.visual-and-mechanical-inspection.equipment.resistor.acceptance | Visual and Mechanical Inspection is specified for resistors in acceptance testing at clause 7.20.4.A of ANSI/NETA ATS-2025. Value: resistors. |
| tests.visual-and-mechanical-inspection.equipment.resistor.maintenance | Visual and Mechanical Inspection is specified for resistors in maintenance testing at clause 7.20.4.A of ANSI/NETA MTS-2023. Value: resistors. |
| tests.visual-and-mechanical-inspection.equipment.sectionalizer.acceptance | Visual and Mechanical Inspection is specified for oil automatic line sectionalizers in acceptance testing at clause 7.24.2.A of ANSI/NETA ATS-2025. Value: oil automatic line sectionalizers. |
| tests.visual-and-mechanical-inspection.equipment.sectionalizer.maintenance | Visual and Mechanical Inspection is specified for oil automatic line sectionalizers in maintenance testing at clause 7.24.2.A of ANSI/NETA MTS-2023. Value: oil automatic line sectionalizers. |
| tests.visual-and-mechanical-inspection.equipment.solar.acceptance | Visual and Mechanical Inspection is specified for solar photovoltaic systems in acceptance testing at clause 7.29.A of ANSI/NETA ATS-2025. Value: solar photovoltaic systems. |
| tests.visual-and-mechanical-inspection.equipment.surge.acceptance | Visual and Mechanical Inspection is specified for low-voltage surge protective devices in acceptance testing at clause 7.19.1.A of ANSI/NETA ATS-2025. Value: low-voltage surge protective devices. |
| tests.visual-and-mechanical-inspection.equipment.surge.maintenance | Visual and Mechanical Inspection is specified for low-voltage surge protective devices in maintenance testing at clause 7.19.1.A of ANSI/NETA MTS-2023. Value: low-voltage surge protective devices. |
| tests.visual-and-mechanical-inspection.equipment.ups.acceptance | Visual and Mechanical Inspection is specified for uninterruptible power systems in acceptance testing at clause 7.22.2.A of ANSI/NETA ATS-2025. Value: uninterruptible power systems. |
| tests.visual-and-mechanical-inspection.equipment.ups.maintenance | Visual and Mechanical Inspection is specified for uninterruptible power systems in maintenance testing at clause 7.22.2.A of ANSI/NETA MTS-2023. Value: uninterruptible power systems. |
| tests.visual-and-mechanical-inspection.governed-by.ansi-c12-1 | Visual and Mechanical Inspection is addressed in ANSI C12.1-2026. |
| tests.visual-and-mechanical-inspection.governed-by.ansi-neta-ats | Visual and Mechanical Inspection is addressed in ANSI/NETA ATS-2025. |
| tests.visual-and-mechanical-inspection.governed-by.ansi-neta-ecs | Visual and Mechanical Inspection is addressed in ANSI/NETA ECS-2024. |
| tests.visual-and-mechanical-inspection.governed-by.ansi-neta-mts | Visual and Mechanical Inspection is addressed in ANSI/NETA MTS-2023. |
| tests.visual-and-mechanical-inspection.governed-by.faa-ac-150-5345-10h | Visual and Mechanical Inspection is addressed in FAA AC 150/5345-10H. |
| tests.visual-and-mechanical-inspection.governed-by.ieee-946 | Visual and Mechanical Inspection is addressed in IEEE 946-2020. |
| tests.visual-and-mechanical-inspection.governed-by.ieee-c57-13 | Visual and Mechanical Inspection is addressed in IEEE C57.13-2016. |
| tests.visual-and-mechanical-inspection.governed-by.ieee-c57-18-10 | Visual and Mechanical Inspection is addressed in IEEE C57.18.10-2021. |
| tests.visual-and-mechanical-inspection.title | The test method is named Visual and Mechanical Inspection. Value: Visual and Mechanical Inspection. |
Winding Resistance
| Record | Statement |
|---|---|
| tests.winding-resistance.equipment.reactor.acceptance | Winding Resistance is specified for dry-type shunt and current-limiting reactors in acceptance testing at clause 7.20.3.1.B.3 of ANSI/NETA ATS-2025. Value: dry-type shunt and current-limiting reactors. |
| tests.winding-resistance.equipment.reactor.maintenance | Winding Resistance is specified for dry-type shunt and current-limiting reactors in maintenance testing at clause 7.20.3.1.B.3 of ANSI/NETA MTS-2023. Value: dry-type shunt and current-limiting reactors. |
| tests.winding-resistance.governed-by.ansi-neta-ats | Winding Resistance is addressed in ANSI/NETA ATS-2025. |
| tests.winding-resistance.governed-by.ansi-neta-mts | Winding Resistance is addressed in ANSI/NETA MTS-2023. |
| tests.winding-resistance.governed-by.ieee-c57-13 | Winding Resistance is addressed in IEEE C57.13-2016. |
| tests.winding-resistance.governed-by.ieee-c57-13-1 | Winding Resistance is addressed in IEEE C57.13.1-2017. |
| tests.winding-resistance.governed-by.ieee-c57-15 | Winding Resistance is addressed in IEEE/IEC C57.15-2017. |
| tests.winding-resistance.ieeec57-12-90.cold-temperature | Clause 5.1 of IEEE C57.12.90-2021 lets the winding temperature for a resistance measurement be taken as the average liquid temperature only after the transformer has stood without excitation or load current for a stated settling period and the top-to-bottom liquid temperature difference is inside a stated limit; windings out of liquid take the average of several thermometers or thermocouples set among the coils and touching the conductors. |
| tests.winding-resistance.ieeec57-12-90.method | Clause 5.3.1 of IEEE C57.12.90-2021 measures winding resistance by the direct-current voltmeter-ammeter method with simultaneous voltage and current readings and with voltmeter leads separate from the current leads and connected at the winding terminals, while clause 5.3.2 allows bridge methods. |
| tests.winding-resistance.ieeec57-12-90.readings | Clause 5.3.1 of IEEE C57.12.90-2021 takes readings only after the current and voltage have settled, averages several readings, limits the test current to a stated fraction of the rated winding current so that heating does not change the resistance, and magnetizes the core to saturation with direct current first so that a cold measurement and a hot measurement start from the same residual flux. |
| tests.winding-resistance.ieeec57-12-90.reference-temperature | Clause 5.2 of IEEE C57.12.90-2021 converts a measured winding resistance to the reference temperature with a formula whose material constant differs between copper and aluminum conductors, so the conductor material is part of the record. |
| tests.winding-resistance.title | The test method is named Winding Resistance. Value: Winding Resistance. |
Zone Selective Interlocking
| Record | Statement |
|---|---|
| tests.zone-selective-interlocking.governed-by.ansi-neta-ats | Zone Selective Interlocking is addressed in ANSI/NETA ATS-2025. |
| tests.zone-selective-interlocking.governed-by.ansi-neta-mts | Zone Selective Interlocking is addressed in ANSI/NETA MTS-2023. |
| tests.zone-selective-interlocking.title | The test method is named Zone Selective Interlocking. Value: Zone Selective Interlocking. |